VNRC begins Dunklee Pond Dam removal in Rutland

RUTLAND — Removal of the Dunklee Pond Dam on Tenney Brook in the City of Rutland is now underway following a three-year design and permitting process, according to a news release from the Vermont Natural Resources Council (VNRC), Aug. 6.

The dam is classified as a “Significant Hazard Potential Dam,” meaning there is potential for loss of life and “appreciable” economic loss should it fail. Most recently, it has posed a substantial flood risk to nearby homes.

VNRC, in conjunction with Vermont River Conservancy (VRC), has been leading this project since dam owners Michelle and Snehal Shah requested assistance to remove it.

Dam removal will restore the river’s equilibrium, improve water quality and habitat, reduce the risk of a large sediment release to downstream river systems (East Creek, Otter Creek, and ultimately Lake Champlain), and reduce flood and erosion risks to downstream homes.

For almost 300 years, the Dunklee Pond Dam has blocked aquatic organism passage of fish and amphibians.

Removal will reconnect the trout populations upstream and downstream of the dam and restore a wildlife habitat corridor.

Dunklee Pond Dam has a rich history of industry and recreation. It was initially constructed in 1792 to operate a small linseed oil mill, followed by a pencil mill, a lumber mill and tannery, in the 1800s, and then a commercial ice harvesting pond. The dam was then utilized as a swimming and recreation area for Rutland City residents, including for ice hockey by Rutland High School.

Beginning in 2017, City of Rutland officials observed that the dam was exhibiting structural deterioration, with water leakage, causing multiple evacuations of nearby homes due to flood risk. Subsequently it was partially breached on Oct. 29, 2019, before the Halloween flood event in an effort to protect the public and temporarily mitigate dam failure concerns. A rapid inspection following the breach by SLR Engineers of Waterbury indicated that “the dam was now stable but all remaining elements were in poor condition, the spillway had working elements, cracks, missing chunks of concrete and dislodged stones. The retaining walls contained large voids and nearby sink holes were present.”

“There are more than 800 small dams in Vermont that no longer serve a useful purpose,” said Karina Dailey, restoration ecologist at VNRC. “They degrade water quality and aquatic habitat, restrict the movement of fish and other wildlife, and pose a risk to public safety. VNRC is very interested in helping dam owners who want to remove unwanted structures, which can have lasting benefits for entire communities and ecosystems.”

In place of the dam impoundment, a new floodplain and stream channel will be established, where trees and shrubs will be planted. The restored wetland may be planted in the future with some seedlings of Northern White Cedar Swamp from the area above to extend that native vegetation into the recovered area.

The Dunklee Pond Dam project entails removing a 75-foot long and 10-foot high concrete impoundment and approximately 11,300 cubic yards of sediment—followed by 900-foot of channel restoration and 1.9 acres of restored floodplain and wetlands to restore hydrologic connectivity to Tenney Brook.

A downstream fish passage weir at Rotary Park is also planned to address the perched concrete box culvert under Route 7, which is immediately downstream of the dam.

VNRC is leading this project with support from its partners, Vermont River Conservancy, U.S. Fish and Wildlife Service, the Lake Champlain Basin Program, and the VTDEC Ecosystem Restoration Program.

Funding for design, permitting, and construction is being provided by the New England Interstate Water Pollution Control Commission (NEIWPCC) in partnership with the Lake Champlain Basin Program, U.S. Fish and Wildlife Service, the National Fish Passage Program, and

Submitted
The Dunklee Pond Dam seen after it was breached. The dam will soon be removed by VNRC.

Vermont Department of Environmental Conservation – Clean Water Initiative Program. SLR Engineers of Waterbury and Kings Trucking and Excavating of Cambridge are the principal contractors for the project.

For more information about the work VNRC and partner organizations are doing to remove unused and unmaintained dams across Vermont, visit freevermontrivers.org.

Do you want to submit feedback to the editor?

Send Us An Email!

Related Posts

Good news, progress,and more work to come

May 7, 2025
The best news of the week was that Mohsen Madawi was released from detention here in Vermont.  The federal government offered no acceptable justification for Madawi’s detention, and, as a result, Judge Crawford of Vermont’s U.S. District Court freed him. The conditions of his release seem relatively simple: he is now free to go back…

Threading the needle

May 7, 2025
Last Thursday, May 1, the full Senate approved its version of the state budget for the fiscal year beginning July 1 with numerous changes from the House. On Friday the House and Senate appointed a conference committee (three House and three Senate members) to work out the differences between the two chambers. Once that happens,…

Sanders introduces Medicare for All

May 7, 2025
U.S. Senator Bernie Sanders, ranking member of the Senate Committee on Health, Education, Labor, and Pensions (HELP), alongside Rep. Pramila Jayapal (D-Wash.) and Rep. Debbie Dingell (D-Mich.), introduced the Medicare for All Act last Tuesday, April 29. Hundreds of nurses, health care providers and workers from around the nation joined the lawmakers for a press conference in…

Why did the herp cross the road? ‘Big Nights’ mean big risks for amphibians and reptiles

May 7, 2025
By Theresa Golub Editor’s note: This story is via Community News Service in partnership with Vermont State University Castleton. Across Vermont, the songs of spring peepers marking the change in seasons. Temperatures rise, snow melts and water runs into the dips and divots of the land to form vernal pools.  Biologists call those springtime basins the…