RUTLAND— Plans to complete the City Creek Path are underway.

The City Creek Path has been 10 years in the making. Once completed, it will be a paved, handicapped-accessible path that connects Giorgetti Park to the College of Saint Joseph.

A new 0.3-mile segment, known as Segment 4 of the total 2.1 mile trail, is going out to bid this summer while another 0.5-mile segment, called Segment 5, is in the engineering phase.

The path is broken into five segments to allow time for funding and project approval. Segments 1 and 2 are done while Segment 3 will be last.

“We as a city have supported their efforts right along,” said Rutland City Mayor David Allaire. “It’s a tremendous draw not only for recreational purposes and tourists to come in but it’s also an enhancement for the community itself.”

Getting the project to the finish line has been a slow process due to the number of approvals and funding needed by the state and local officials.

“Although it might not seem like it to the public, it’s steadily moving,” said Susan Schreibman, one of the organizers behind the trail.

The project started with a $125,000 grant from a town fund. The project managers have received $2.5 million in state and federal funds plus another $500,000 from donations.

The organizers say Segment 4 will cost $250,000 to $300,000 to construct with engineering.

“There’s a need (for this trail). We can’t hide from the fact that obesity in Rutland County is high. This is a way of getting folks to be more active,” said Paul Gallo, who is overseeing the project with Schreibman.

This project is one of several initiatives underway to enhance recreation in Rutland.

A proposal to reduce the number of lanes on Route 4 from four to three to create a bike lane between West Rutland and Rutland failed in a 3-2 vote May 29 by the Rutland Town Select Board.

Gallo expects the City Creek Path to be done in the next four to six years.

Schreibman, who formerly worked with the Regional Planning Commission, is proud of what’s been done so far.

“This is exactly what we hoped for and envisioned. It’s a beautiful path for the city,” she said.

Do you want to submit feedback to the editor?

Send Us An Email!

Related Posts

Weather impacts Killington mid-week skiing

May 8, 2025
Killington Resort planned on keeping its lifts running during the week until May 11 (then weekends only), but rain and warm temps over the last several days have taken a serious toll on its snowpack. Therefore, Killington Resort will be closed Thursday, May 8, and Friday, May 9, to preserve what they have left and…

How Killington became The Beast: Part 9

May 7, 2025
Snow, summer, and snowshed: 1960 saw fast progress How Killington became The Beast: Part 9 By Karen D. Lorentz Editor’s Note: This is the ninth segment of an 11-part series on the factors that enabled Killington to become The Beast of the East. Quotations are from author interviews in the 1980s for the book “Killington,…

Woodstock Foundation honors the winners of new Rockefeller Legacy Scholarship

May 7, 2025
Three Woodstock Union High School students were honored on April 30 for their visionary ideas about shaping Vermont’s future as the first recipients of the Laurance and Mary Rockefeller Legacy Scholarship, a new annual essay competition created to honor the Rockefellers’ lasting impact on the community. The scholarship program was launched in 2025 by The…

Jimmy LeSage Memorial Scholarship awarded to Brycen Gandin of Mendon

May 7, 2025
The first-ever Jimmy LeSage Memorial Scholarship, a $2,500 award created to honor the life and legacy of wellness pioneer Jimmy LeSage, has been awarded to Brycen Gandin, a graduating senior at Rutland Senior High School. Brycen, a resident of Mendon, can use the scholarship toward the college of his choice this coming academic year. Brycen was…