This weekly report is a list of planned construction activities that will have traffic impacts on state highways throughout Vermont. Please remember to drive safely in all work zones. Lives depend on it.

I-89 Hartford – Sharon

A resurfacing project continues. Nighttime milling operations will require lane reductions on I-89 northbound and southbound from the VT/NH border to just north of Exit 1. A speed reduction to 55 mph will be enforced when lane closures are in effect.

I-89 Sharon

A bridge rehabilitation project continues. Traffic is reduced to one lane in each direction; crossovers are being utilized. Motorists should be aware of a work zone speed reduction.

I-91 Hartford

Motorists can expect continuous lane closures on I-91 northbound and southbound between Exits 12 and 11 in Hartford as crews continue bridge repairs at bridge #44 over U.S. 4, VT 14, the New England Central railroad, and the White River.

Cavendish – Weathersfield

A roadway reclaim project is underway. Motorists should expect alternating one-way traffic at multiple locations throughout the length of the project. Please use caution as paved, milled (scarified), and gravel surfaces exist within the project area. Moderate delays expected. Add extra time to your travel plans.

Chester – Springfield

Multiple bridge replacement projects are underway on VT 11 between VT 103 in Chester and VT 106 in Springfield. Please expect one-way alternating traffic at various points along this route. Anticipate delays.  

Fair Haven – Rutland

Single-lane closures are planned on U.S. 4 in both directions for paving operations, including partial and full exit ramp closures. A crossover traffic pattern is in place at the railroad crossing on divided highway U.S. 4 (approximately ½ mile from the junction of U.S. 4 and U.S. 7), with a reduced speed of 35 mph. Motorists should use caution on U.S. 4 as they encounter grooved pavement on exit ramps and the mainline.

Hartford

Motorists should expect lane and shoulder closures and alternating one-way traffic along Sykes Mountain Avenue as crews continue work on the roundabouts and sidewalk. Expect noise and minimal delays from 7 a.m. to 6 p.m.

Pittsford

Multiple activities for roadway reconstruction along U.S. 7 this week. Motorists should proceed with caution as they navigate new traffic patterns and lane shifts throughout the project. Expect alternating one-way traffic with minor delays. A speed reduction to 35 mph remains in effect. 

Proctor

The North Street bridge project is underway. A short-term road closure of North Street at the location of the bridge will be in effect beginning Tuesday, May 26. A signed detour will be in place.

Stockbridge

On Monday, May 24, district crews will pave a one-mile stretch of VT 100 beginning at its intersection with VT 107 progressing west. Motorists will encounter one-way alternating traffic and should plan on delays for the day.

Weston

A paving project continues along VT 100. Motorists should expect alternating one-way traffic during the day.

Woodstock

A resurfacing project is underway. Motorists should expect intermittent lane closures and alternate one-way traffic controlled by flaggers on U.S. 4, VT 12, and VT 106 between 7 a.m. and 7 p.m.

Do you want to submit feedback to the editor?

Send Us An Email!

Related Posts

Weather impacts Killington mid-week skiing

May 8, 2025
Killington Resort planned on keeping its lifts running during the week until May 11 (then weekends only), but rain and warm temps over the last several days have taken a serious toll on its snowpack. Therefore, Killington Resort will be closed Thursday, May 8, and Friday, May 9, to preserve what they have left and…

How Killington became The Beast: Part 9

May 7, 2025
Snow, summer, and snowshed: 1960 saw fast progress How Killington became The Beast: Part 9 By Karen D. Lorentz Editor’s Note: This is the ninth segment of an 11-part series on the factors that enabled Killington to become The Beast of the East. Quotations are from author interviews in the 1980s for the book “Killington,…

Woodstock Foundation honors the winners of new Rockefeller Legacy Scholarship

May 7, 2025
Three Woodstock Union High School students were honored on April 30 for their visionary ideas about shaping Vermont’s future as the first recipients of the Laurance and Mary Rockefeller Legacy Scholarship, a new annual essay competition created to honor the Rockefellers’ lasting impact on the community. The scholarship program was launched in 2025 by The…

Jimmy LeSage Memorial Scholarship awarded to Brycen Gandin of Mendon

May 7, 2025
The first-ever Jimmy LeSage Memorial Scholarship, a $2,500 award created to honor the life and legacy of wellness pioneer Jimmy LeSage, has been awarded to Brycen Gandin, a graduating senior at Rutland Senior High School. Brycen, a resident of Mendon, can use the scholarship toward the college of his choice this coming academic year. Brycen was…