Connolly Pond Dam is removed for public safety in Shrewsbury

 

Engineers, contractors, landowners, and scientists gathered Aug. 22 for the post-construction meeting and site walk for the removal of Connolly Pond Dam in Shrewsbury. Construction was completed, the dam has been removed, and the channel is free-flowing. 

The dam was removed in the interest of public safety to reduce flood risk, and to reconnect and restore a headwater tributary to the Mill River, which ultimately flows to the Otter Creek and then Lake Champlain.

 In 2020, the Vermont Dam Safety classified the dam as in poor condition with a significant hazard potential dam rating. The dam safety inspection stated, “Failure could result in damage and economic losses due to shallow flooding of property and overtopping of multiple road crossings.” 

The dam is reported to have been constructed about 1965 for fire suppression, and to provide a water source for farm crops and livestock, and as a pond for recreation. 

In addition to reconnecting the headwaters to the Mill River and ultimately Lake Champlain, many co-benefits result from dam removals including restoring natural sediment transport, reduced erosion, restored passageways for aquatic organisms,, reconnection with the floodplain to support flood resilience, restored wetlands, stream channel processes, and a restored ecosystem with increased biodiversity, according to experts. 

“Restoring natural river processes including water, sediment, nutrient and wildlife transport through derelict dam removal is tremendously rewarding work because you can observe the restored river functions come back almost instantaneously,” said Karina Dailey, restoration ecologist with the Vermont Natural Resources Council. 

“We saw some small fish in the new channel and moving around upstream on our last site walk. We installed a few extra large wood pieces and boulders in wet areas to break up flow paths to limit future erosion. It will be great to watch it all continue to stabilize and come back to life with pulses of the flow and sediment moving through the area,” said Roy Schiff, project engineer.

The earth from the dam embankment will be used to fill and re-form the east and west valley walls, therefore no sediment is being hauled off site, which also saved on dam removal costs.

The landowner, Amy Leah de Camp-Thomas, shared, “What an incredibly beautiful place our old pond/dam has become. It is so clear that the work (from its start a few years ago through to the last day of construction a few days ago) was completed with thoughtfulness and care. We are absolutely in love with the outcome.”

Karina Dailey, restoration ecologist with VNRC, has managed the project in partnership with the landowners. The engineering firm was SLR Consulting of Waterbury, and the construction firm completing the removal was Birdseye Construction of Richmond. 

Funding for design, permitting, and construction has been provided by Vermont Natural Resources Council, NEIWPCC in partnership with the Lake Champlain Basin Program, the Vermont Dept. of Environmental Conservation through Watershed United Vermont, US Fish and Wildlife Service, and the Landowners.

Do you want to submit feedback to the editor?

Send Us An Email!

Related Posts

Officials strongly recommend limiting time outdoors in high-risk areas due to EEE threat

September 4, 2024
High-risk towns include Alburgh, Burlington, Colchester and Swanton  Health officials began strongly recommending people in towns at high risk for eastern equine encephalitis (EEE) avoid spending time outdoors as much as possible between 6 p.m. and 6 a.m. to avoid mosquitoes that could carry the virus, according to a Aug. 26 news release. If going…

Where is the state road construction? 

September 4, 2024
The Vermont Agency of Transportation (VTrans) published its weekly report of planned construction activities that will impact traffic on state highways and interstates throughout Vermont, Sept. 3-6 and ongoing. I-89 Royalton: Work continues on the northbound and southbound I-89 bridges near Exit 3 in Royalton. A new traffic pattern is in effect until fall 2025:…

Michael Costa named CEO at Gifford

September 4, 2024
Michael Costa will join Gifford Health Care as president and chief executive officer on Oct. 14, Gifford’s board of directors announced Aug. 29. Costa will succeed Dan Bennett, who will retire from the role at the Randolph hospital on Oct. 11. “Michael is a great fit for Gifford and our supportive, community-focused culture,” said Gifford…

Killington  Resort and Pico Mountain honor employees at annual Milestone Party

September 4, 2024
By Brooke Geery, Killington Resort Each year, Killington Resort celebrates its team members who have reached significant five-year milestones in their careers at The Beast. A party is thrown, complete with gifts from Yeti, a delicious steak dinner from Southside Steakhouse and an evening of fun and games at Stonehedge Indoor Golf. The 2024 gala,…