Vermont Gas pulls plug on pipeline to New York

Decision expected to delay timeline for natural gas to reach Rutland

By John Herrick

Vermont Gas Systems has abandoned its plan to bring natural gas under Lake Champlain to a New York paper mill after the plant withdrew its financial support.
Vermont Gas had proposed building a pipeline from Middlebury to the International Paper facility in Ticonderoga, New York. The mill was to pay a significant portion of the pipeline cost, but recent construction estimates proved unacceptable to the plant’s operators.
The utility’s latest cost estimate pegs the project at $105 million — up from the original $64 million estimate. On Monday, Feb. 9, International Paper told Vermont Gas it was terminating its financial agreement to pay for nearly the entire project.
“This project was designed primarily to serve International Paper. Without their continued participation, the project doesn’t make sense anymore,” Vermont Gas CEO Don Rendall said Tuesday.
The project would have served fewer than 200 Vermont residents before crossing beneath Lake Champlain to the paper mill. The project has garnered political support as a stepping stone for delivering gas to Vermont customers in Rutland, but has seen pushback from landowners and environmental groups.
Gov. Peter Shumlin, who has consistently backed the pipeline, said he supports the company’s decision to “scrub the numbers” and make sure the project makes sense for ratepayers.
“I am gratified that Vermont Gas will be putting a renewed focus on offering strong public benefits and a choice for Vermonters of natural gas service through its ongoing expansion to Middlebury and continued exploration of how to drive farther south to Rutland,” Shumlin said in a statement.
International Paper planned to contribute $25 million to $31 million toward phase one. According to company testimony filed with regulators last September, the rate impacts for existing customers are estimated to rise 3.6 percent in 2015 to 10.2 percent without phase two. Rendall said the company will still have to file a rate case with regulators before the impacts are finalized. He said the overall cost of the initial project will not change.
The cost for the first phase of the project has already jumped by 78 percent to $154 million, largely due to rising construction costs. The Public Service Board will consider whether to reevaluate the company’s permit, which could include making changes or revoking it altogether.
Rendall said Vermont Gas still intends to seek ways to bring natural gas service to the Rutland area and has not ruled out construction of a pipeline, although the timeline will likely be extended.

Do you want to submit feedback to the editor?

Send Us An Email!

Related Posts

Vermont receives $5.3 million in federal grants to expand internet access across the state

November 27, 2024
By Klara Bauters / VTDigger Vermont has been awarded $5.3 million from the federal government to implement its Digital Equity Plan — which outlines how the state will provide individuals and communities with the tools and skills necessary to benefit from meaningful access to affordable, reliable, high-speed internet service. “Internet and broadband. It’s no longer…

Experts fear Trump environmental policies could undermine Vt’s efforts

November 27, 2024
By Emma Cotton/VTDigger As Donald Trump prepares to return to the presidency, experts worry that his climate and environmental policy goals could destabilize ongoing work in Vermont. The president-elect campaigned on tossing out policies related to climate change and loosening or abandoning environmental regulations. As a small state, Vermont leans on federal funding and regulatory frameworks…

VTSU sees 20% enrollment growth in plumbing, electrical apprenticeship programs

November 27, 2024
As the state kicked off Apprenticeship Week last week, Vermont State University (VTSU) announced that its plumbing and electrical registered apprenticeship programs have grown over 20% in two years. Enrollment for the current academic year is at a record high of over 870 apprentices after multiple years of sustained growth. “Vermont State University is dedicated…

Outdoor recreation organizations implore courts to support public access to trails in Vermont

November 27, 2024
A coalition of outdoor recreation organizations led by the Vermont Trails and Greenways Council (VTGC), issued a statement Nov. 18 urging the Vermont Supreme Court to carefully consider the long-term implications of its upcoming ruling regarding the maintenance of public access trails on private land.  The case, which involves the use of a “legal trail” maintained by the town that crosses…