On August 21, 2024
Uncategorized

Full Quechee Road rehab estimated at $6 million, options considered

Submitted

By Curt Peterson

Perhaps because of traffic volume on Quechee Road, and although there are much worse and less-used Hartland roads, conditions on the main route from Hartland Three Corners to Quechee village is the topic of frequent complaints on the local listserv.

The section between Gilson Road and Webster Road is particularly bad, featuring cracks, potholes, large patches of missing asphalt layers and failing road edges. For some years the common refrain has been “poor base that has to be replaced.”

At Monday’s Select Board meeting Scott Williams of Pathways Consulting in Lebanon reviewed a current eight-page engineering report regarding a detailed study of the 6-mile road that was financed with American Rescue Plan Act (ARPA) funds. The tests and engineering were performed by M&W Soils Engineering of Charlestown, and the report authored by Randal Rhodes.

Williams described how the engineers drilled approximately 40 holes 2-3 inches in diameter and up to 21/2 feet deep that took soil samples from the actual roadbed. The soil was then analyzed for components in a laboratory.

What they found was multiple layers of asphalt over a sub-base of gravelly sand from 18  inches to 30 inches deep, originally meant as base for a gravel road. “Movement” within this layer causes cracking in the road surface. When ruts are formed and overlaid with asphalt, Williams said, they remain as non-conforming parts of the base, exacerbating the movement and cracking effect.

“The overlayment on this road is actually in good condition,” he said. “It’s what’s underneath that’s causing the problem.”

The problematic section of Quechee Road has ledge on one side, and a steep slope on the other. Williams said inadequate ditching, ponding of water on the road, and subsidence on the slope side are also factors in the obvious surface failure.

He offered four options the town might use on the road.

Option 1: just to do another 1- to 11/-inch layer of asphalt paving over the entire road.

Option 2: involved “inlay and overlay,” milling the road surface to assist in bonding the new application to the existing road surface.

Option 3: remove and reclaim the existing base and overlay before replacing, adding 4 inches of gravel or crushed stone and overlaying with new asphalt.  “This option would not be very effective for the bad areas,” Williams said.

Option 4: Excavate 18 inches (maybe 24 inches) of material and replace with appropriate sub-grade and sub-base component before overlaying with new asphalt. “This will be very expensive,” Williams said. “But if you consider your current ongoing and repetitive costs, you will save money in the long term.”

His rough estimate for Option 4 was $1 million per mile, or $6 million total, including a 20% contingency for unexpected issues.

Williams recommends doing the entire road, or at least significant sections, rather than limiting the project to the bad areas, as contractor costs for multiple smaller jobs will be higher.

“The contractor will probably execute the work one lane at a time, for minimum traffic disruption,” he said.

The culverts that were inspected are also in bad shape — some clogged, about 30% rusted through. These issues and some guardrail damage would be mitigated separately, by the town.

Williams offered his help when the town begins planning and budgeting for the work.

Do you want to submit feedback to the editor?

Send Us An Email!

Related Posts

Most tasks in Vermont hazard mitigation plan left incomplete, auditor says

September 18, 2024
By Peter D’Auria/VTDigger In 2018, the state of Vermont released a plan outlining how it should prepare for natural disasters. The State Hazard Mitigation Plan lays out 24 strategies, separated into 96 discrete actions, to address risk factors for natural disasters. Those actions included improving flood resilience, strengthening building design standards and educating local communities about potential hazards,…

Worldly baker teaches bagel making

September 18, 2024
By Curt Peterson A dozen Hartlanders joined “master baker” Jeffrey Hamelman at the public pizza oven on Saturday morning, Sept. 7, bent on learning how to make bagels. Ten women, one rising 8-year-old girl, and an aging male journalist brought a short list of kitchen equipment. One of the women, Sara Fuschetto, is a breadmaker…

Attempting to avoid dogs, Ram hits man

September 18, 2024
On Wednesday, Sept. 11 at 5:45 a.m., police responded to a vehicle vs. pedestrian crash on Lake Dunmore Road near Fernville Road in the town of Leicester.  Investigation revealed Timothy Lester, 54 of Leicester, was walking on the side of the northbound lane while Benjamin Kandzior, 43 of Leicester, was traveling south in a Dodge Ram…

Daniel Banyai arrested for violating conditions of release on pending aggravated assault charge

September 18, 2024
Banyai was arrested by the same Pawlet constable he’s charged with assaulting By Ethan Weinstein/VTDigger Daniel Banyai, 51, was arrested Monday, Sept. 9, for violating conditions of release on his pending felony charge of aggravated assault against a police officer, according to a press release by Pawlet Constable Thomas Covino. Covino is the same officer whom Banyai is…