On August 14, 2024
Featured

Killington Road preps for paving, will be closed Aug. 19-25

Killington Road from Route 4 to Anthony Way will close again next week for paving. It will close starting at 7 a.m., Monday, Aug. 19 and reopen Monday, Aug. 26, paved with some construction work continuing on the sides, according to Killington Public Works Director Abbie Sherman.

“A lot of the project is starting to close up as we complete the sewer line and drainage line along the edges of the roadway,” wrote Markowski Excavating, Inc. in a news release. “We plan to wrap up the sewer line on Monday [Aug. 12] and decommission the temporary sewer line we installed earlier on. Once connected, expect more sand and gravel to be hauled on site to finalize the installation of the road materials.”

By Polly Mikula

This week crews will also embark on final swale clean up along the western side of the road with gravel hauled in as they prep for the paved walkway and begin installing the retaining wall below Killington Sports. Blocks have been delivered to the site throughout the last two weeks but “we are still limited on installing if fully as the last power pole at the bottom still needs to be moved (currently scheduled for the week of August 26),” Markowski noted.

On Tuesday, Aug. 13, crews began milling at the intersection with Route 4 and the south end of the project near Anthony Way in prep for paving the following week.

Starting Wednesday, Aug. 14, work will extend into Route 4.

“We need to install a 3-foot culvert that crosses Route 4 and ties into an existing catch basin on just short of the Route 100 intersection. Multiple flaggers will be on site, so expect delays as we single lane the road. This will continue through Friday,” Markowski said.

The walway and Route 4 culvert crossing will be paved next week, which will cause intermitted traffic delays.

Pike Industries has been contracted to do the paving.

Do you want to submit feedback to the editor?

Send Us An Email!

Related Posts

Most tasks in Vermont hazard mitigation plan left incomplete, auditor says

September 18, 2024
By Peter D’Auria/VTDigger In 2018, the state of Vermont released a plan outlining how it should prepare for natural disasters. The State Hazard Mitigation Plan lays out 24 strategies, separated into 96 discrete actions, to address risk factors for natural disasters. Those actions included improving flood resilience, strengthening building design standards and educating local communities about potential hazards,…

Worldly baker teaches bagel making

September 18, 2024
By Curt Peterson A dozen Hartlanders joined “master baker” Jeffrey Hamelman at the public pizza oven on Saturday morning, Sept. 7, bent on learning how to make bagels. Ten women, one rising 8-year-old girl, and an aging male journalist brought a short list of kitchen equipment. One of the women, Sara Fuschetto, is a breadmaker…

Attempting to avoid dogs, Ram hits man

September 18, 2024
On Wednesday, Sept. 11 at 5:45 a.m., police responded to a vehicle vs. pedestrian crash on Lake Dunmore Road near Fernville Road in the town of Leicester.  Investigation revealed Timothy Lester, 54 of Leicester, was walking on the side of the northbound lane while Benjamin Kandzior, 43 of Leicester, was traveling south in a Dodge Ram…

Daniel Banyai arrested for violating conditions of release on pending aggravated assault charge

September 18, 2024
Banyai was arrested by the same Pawlet constable he’s charged with assaulting By Ethan Weinstein/VTDigger Daniel Banyai, 51, was arrested Monday, Sept. 9, for violating conditions of release on his pending felony charge of aggravated assault against a police officer, according to a press release by Pawlet Constable Thomas Covino. Covino is the same officer whom Banyai is…