On July 15, 2020

Storm water solvable at new Woodstock school site, consultants find

By Curt Peterson

The Windsor Central Unified Union School District (WCUUSD) building and grounds committee will tell the full school board at its next meeting on Aug. 3 that concerns about drainage, wetlands, and storm water management can be resolved for preliminary approval of state standards, and will let the full board know that the additional $137,000 of remaining donated funds could be spent to determine a realistic cost estimate for construction of the proposed new Middle/High School near the existing structure.

Building and grounds met jointly with the finance committee via Zoom on Thursday, July 9 to hear a presentation by Andres Torizzo, co-principal of Watershed Consultants in Burlington.

The consulting firm was engaged to study the hydro-related issues when board member Jim Haff (Killington), buildings and grounds committee chair, and Killington Town Manager Chet Hagenbarth, pointed out that these issues and the Ottauquechee River corridor, which runs through the site, needed to be dealt with before the board considers moving forward with further design and financing of the new school.

Architect Leigh Sherwood of Lavallee Bresinger Architects said Wednesday night it turned out to be a “great suggestion.”

Up to this point the board has relied on Sherwood’s original estimate of $68 million for the new school.

The board had committed $10,000 to finance the preliminary stormwater approval process.

Sherwood said he has talked to all the parties involved in the next phase, and told them about the $137,000 budget for producing estimates.

Haff pressed Torizzo for a specific cost estimate regarding the water management solutions he has recommended and submitted to the state for evaluation, but the consultant said he did not have presentable numbers at this point. For example, he said, he was recommending an optional underground storm water filtration system that would save money in the long run, but might add to construction cost. The district would have to decide whether or not to spend the money now to save costs later.

Haff then asked Sherwood, “You gave us an estimated cost for the new building two years ago,” he said. “Did that include enough money to pay for the work [Torizzo] is proposing?”

Sherwood admitted the amount of money included in the per-square foot figure two years ago was based purely on historical costs in other projects, not on WCUUSD’s specific site or plans.

In other towns, such Burlington, the true cost of construction have been much higher than initial estimates.

There was some discussion about how the Covid-19 pandemic might affect both the design and the construction schedule for the new building. Agency of Education guidelines for opening elementary, middle and high schools are still evolving, so predicting the virus’s effect is tricky.

“We can’t expect the board to vote on building the new school without having a better idea of the actual cost,” Haff told the Mountain Times, “especially now, in the middle of a pandemic.”

Do you want to submit feedback to the editor?

Send Us An Email!

Related Posts

Killington 1970s skiers reunite at Charity’s 1887 Saloon to celebrate lifelong memories, adventures, and cherished friendships at Charity’s 1887 Saloon

October 17, 2024
By Victoria Gaither Saturday, Oct. 19, at 2 p.m.—KILLINGTON— Charity’s 1887 Saloon will be the scene for the Killington 1970s Reunion social event. The event came about after organizer Jack Oliver attended his 50th high school reunion. Oliver explained, “I had never attended one before and was always reluctant to do so but enjoyed it.”…

Vermont Adaptive Ski and Sports seeks winter volunteer-instructors

October 17, 2024
Instructor training begins in November for skiing, snowboarding and winter sports KILLINGTON — Vermont Adaptive Ski and Sports, the largest year-round disabled sports nonprofit organization in Vermont to offer daily, year-round sports and recreation for people with disabilities, is looking for energetic winter volunteer-instructors who have a dedicated passion for sports and who want to…

Enter to win the 2025 Vermont Writers’ Prize

October 17, 2024
Annual prizes for poetry and prose celebrating Vermont are awarded by Green Mountain Power and Vermont Magazine. Winning entries in each category are published in the summer issue of Vermont Magazine and receive $1,250. The deadline to enter is Jan. 1, 2025. Entries are open for the 2025 Vermont Writers’ Prize, awarded each year in…

There’s no place like the stage: twists, turns, and punchlines from Vermont to Hollywood and back again – Nick Wevursky explains

October 17, 2024
Nick Wevursky, a standup comic in Rutland County, has always had a talent for finding humor in everyday life. Growing up across small towns in the Green Mountain state, he balanced activities like tending horse farms and snowboarding at Stratton, where his sister was a pro. Even as a kid, he loved making people laugh,…