On June 19, 2024
Featured

Two blasts a day likely this week on Killington Road

“With the second drill on site, expect two blasts a day,” wrote Markowski Excavating, Inc. in a news release before the week began. “First one will be around 10:30-12 noon and the second will be around 1:30-3 p.m.” 

Traffic will be stopped on Route 4 during the blasts.

Markowski will continue to haul blasted rock off site during the week and on Saturday mornings. 

“Water line installation will also continue this week then switch over to installing more sewer line along the east side of the Access Road,” the news release continued. “In addition, as the utilities are installed, we will begin hauling sand and gravels from Route 4 up the Access Road.”

The following week, beginning June 17, should be the end of major drilling and blasting. “If any remaining blasts are needed, it will be up by Anthony Way and will not require stopping traffic on Route 4,” wrote Markowski.

Sewer line installation will continue. 

“In addition, we will be also working to install the future water line along the west side of the Access Road. Again, as these two lines are installed, we will continue to install the sand and gravel layers which will be just below final pavement layer,” the release continued.

A continuation of dust control will occur as needed with warmer and drier weather.

East Mountain Road work

The repairs on East Mountain Road from last summer flooding continues, accoring to Abbie Sherman, public works director for the town of Killington. This week Mosher Excavating will change the signs from “Road Closed” to “Road Work Ahead.” Delays are expected when passing through the work zone between Bear Mountain Road and Route 4. 

During the week of June 24, that section of road will be closed for about a day while two culverts are installed, Sherman noted.

Do you want to submit feedback to the editor?

Send Us An Email!

Related Posts

Tips to maintaining your bike

September 27, 2024
Staff report So, you bought a mountain bike. Well done! You’ve now got a few epic rides under your belt. Excellent. But now you wonder how to best protect your investment and keep it rolling like new.  While there are many expert bike mechanics around locally that can help, here are a few basic things…

Agency of Trans awards $7.19m in bicycle and pedestrian grants

September 27, 2024
The Vermont Agency of Transportation (AOT) announced Sept. 12 the awards of approximately $7.19 million in grants to municipalities for bicycle and pedestrian infrastructure improvement projects. The combination of construction projects and planning grants will benefit cities and towns statewide with improved transportation connectivity and safety, tangible economic benefits, and additional transportation options for commuters,…

Tour of Pine Hill park: Go clockwise for an extra workout; go counter-clockwise for fun

September 27, 2024
By Shelley Lutz, Pine Hill Partnership board member  Pine Hill Park in Rutland City is one of the original trail networks in Central Vermont and is a must-stop on any mountain biker’s itinerary. The wooded park is 275 acres with 18 miles of mostly singletrack trails dotted with seven unique bridges. If you are an aerobic…

Peninsula Trail and Loop, a scenic tour in the Aqueduct Trails

September 27, 2024
By Ada Mahood, Woodstock Mountain Bike Team Peninsula is a trail that is perfect for beginners and intermediates riding in Woodstock. The scenery is quite amazing, especially in the fall. It starts up a short hill, then over some roots and up a short technical part before ending in the mossy lands of the Peninsula…