By Pat Wise - Construction continues at the base of Killington Road where it intersects with Route 4.

Drilling and blasting will continue this week at the intersection of Route 4 and Killington Road in Killington. A detour remains in place via West Hill Road. 

As the project approaches the scheduled end date of July 8, work to haul out rock will occur on Saturdays till about noon time going forward, Markowski Excavating, Inc. explained.

“Although the second drill rig was supposed to arrive last week, it will be on site either Monday or Tuesday. [We] expect delivery of the drill and another delivery of blasting matts to arrive either of these days,” Markowski continued in a update in advance of this week’s roadwork. “They will start drilling down near Route 4, then work up the east side of the access road to remove remaining ledge. Due to timing, there may be multiple blasts per day if it lines up. Traffic will be stopped for those shots, so be aware of flaggers on the road to stop vehicles for 5-10 minutes.”

Otherwise, as has been the case for the past month, there’ll be one blast daily between 11 a.m. and 12-noon, “but if there is any unforeseen delays it could be as late as 1 p.m.,” Markowski noted.

Work this week will focus on installing the sewer structures and pipe along Route 4. 

“We will then focus the second half of the week on installing water and sewer line away from Route 4 south on the Access Road. As this progresses, expect more sand and gravels to be installed to build up the road base,” Markowski noted.

Work for the following week, beginning June 17, will be a continuation of drilling and blasting rock with dump trucks entering and exiting the site to load out rock.

Sewer line installation will continue to be installed up the east side of Killington Road. 

“In addition, we will be also working to install the future water line along the west side of the Access Road. Again, as these two lines are installed, we will continue to install the sand and gravel layers which will be just below final pavement layer,” Markowski noted.

A continuation of dust control will occur as needed with warmer and drier weather.

Do you want to submit feedback to the editor?

Send Us An Email!

Related Posts

Overridden!

June 26, 2024
Last Monday the Vermont Legislature reconvened to override six out of the seven gubernatorial vetoes issued since the regular session ended a month ago. Clearly the Democratic supermajority in the legislature and Governor Scott are not on the same page and see such issues as affordability differently. Among the bills overridden were ones increasing the…

Margaret Schiessl, 88

June 26, 2024
After a well-lived life, long-time Killington Vermont resident Margaret “Omi” Schiessl passed away at age 88 on March 4, 2024, in Parrish, Florida.  Schiessl’s testament in life was to spread love to her family and friends. She was a beloved wife, mother, Oma, sister, and friend born on Jan. 2, 1936, in Nürtingen, Germany. She…

Kevin Hewitt named Killington highway foreman 

June 26, 2024
The town of Killington announced the appointment of Kevin Hewitt as the new highway foreman as of June 24. Hewitt is currently employed in the town’s highway department and brings an abundance of experience in infrastructure maintenance and construction management to the team, with a strong foundation of knowledge of Killington's needs, the town stated…

Vermont’s junior high rodeo finalists head to first-ever national championship

June 26, 2024
Four Vermont girls from New England’s only rodeo team will face competitors from most U.S. states and abroad By Juan Vega de Soto/VTDigger A weeklong junior high rodeo is being held this week in Des Moines, Iowa. Events run Sunday, June 23 through Saturday, June 29 and Vermont had representation on that national stage for the…