Blasting to begin on Killington Road this week

By Jason Mikula — The west side of Killington Road is dug out, blasting to come.

Work to resume on East Mountain Road next week, delays expected

Staff report

With warmer weather in the forecast this week, Markowski Excavating, Inc. will continue excavation at the base of Killington Road up to Anthony Way. However, this week they’ll likely start blasting ledge that they encountered.

“Last week, we received a couple loads of blasting matts,” wrote Markowski Excavating, Inc.in a news release. “This week a rock drill will arrive on site and drilling will commence. Once on site, we will start preparing for blasting either by the end of the week or start of the following depending on the schedule for the driller’s arrival. During blasting activities, expect intermittent delays on Route 4 and Route 100. Traffic will be stopped for 10 minutes during the blasting. This will happen once a day. A time during the day has yet to be determined, but we will attempt to keep it consistent daily.”

This week the installation of the future waterline that will extend along the west edge of the road will also begin.

Work for the following week, starting May 6, blasting will likely happen daily. 

“We will be excavating more rock than dirt at this junction of the project as well,” the release continued. “The waterline will continue to progress up the hill with sand and gravels for the road base … In addition, some sewer line installation and structures will be installed along the intersection of Route 4 and the Access Road.”

The base of Killington Road where it intersects with Route 4 will remain closed into July.

East Mountain Road

Craig Mosher, owner of Mosher Excavating, announced Tuesday, April 30 that work would again resume on East Mountain Road next week. 

Mosher was selected by the Select Board to coordinate the repair of East Mountain Road and its offshoots after the severe flooding that wiped out sections of the road last July. 

More details of the repairs and timeline will be available next week, Mosher said, but added that folks could “expect some delays to begin next week.” 

Do you want to submit feedback to the editor?

Send Us An Email!

Related Posts

Vermont health insurance costs are among the highest in the nation — and rising quickly

September 4, 2024
By Peter D’Auria and Erin Petenko/VTDigger Health insurance prices in Vermont are high — and getting higher. Average premium prices for individual marketplace plans in Vermont are among the highest in the country, according to data from the Centers for Medicare and Medicaid Services, costing more than double the national average, even when federal subsidies are accounted for.  Vermont’s premium…

Lacombe  and Sierman celebrate 45 years at Killington Resort Milestone Party

September 4, 2024
Dave Lacombe in the mountain operations dept. and Keiki Sierman in the accounting dept. celebrated 45 years of working at Killington Resort along with 20 other colleagues who were celebrating five-year work anniversaries. 

State: Vermont needs 24,000-36,000 new homes within five years

September 4, 2024
Housing stock, affordability remain leading factors in impacting needs, study finds  The Department of Housing and Community Development (DHCD) announced Aug. 29 the publication of the Vermont 2025-2029 Statewide Housing Needs Assessment, a five-year document the U.S. Department of Housing and Urban Development (HUD) requires from government entities that receive federal funding. The findings in the report show…

Tom Yennerell named interim Killington town manager

August 28, 2024
By Polly Mikula Starting, Tuesday, Sept. 3 Killington will welcome Tom Yennerell as its new interim town manager. The Select Board approved the contract at its regular meeting Monday, Aug. 26. “Tom will be hired on as an interim town manager, with full powers of a town manager,” said Select Board member Jim Haff. “It’s…