Killington Forward update: base of Killington Road prepped this week, closed starting Monday

“We plan to begin work on the Killington Access Road Project starting April 8,” wrote Tom Markowski of Markowski Excavating, Inc., in a project update April 5. The project will ultimately reduce the grade of the hill on Killington Road from where it intersects with Route 4 to Anthony Way. “Although the first day will be limited to moving equipment and mobilizing some materials. Only half a day of work is expected due to the solar eclipse event Tuesday… Wednesday through Friday will be more shoulder closed work,” he explained.

Killington Road will remain open this week, while crews prep.

“We will be removing snow and adjusting the elevation of an existing catch basin in the ditch line,” Markowski continued. “Also during this time, Lafayette Highway Systems will be working along Route 100, Route 4, West Hill Road and Killington Road installing construction signage in prep for the detour plan.”

“By midday Monday, April 15, the Killington access road will be closed from the intersection with Route 4 up 1,300 feet. At this point, vehicles that wish to go between the access road and Route 4 will have to use West Hill Road.”

The detour is expected to last until July 8.

“More equipment will arrive this week and trucks will be entering and exiting the job site at the Route 4 intersection. Please be cautious of trucks pulling out headed both East and West on Route 4. The turning lanes on Route 4 will be barreled off and inaccessible,” Markowski concluded.


Courtesy Markowski Excavating, Inc.
Map shows planned work at the base of Killington Road for the week of April 8-12.

Do you want to submit feedback to the editor?

Send Us An Email!

Related Posts

Killington Resort announces staff promotions, management additions 

June 4, 2025
Josh Reed  Josh Reed has moved into the role of communications manager. Reed has been part of the Killington team since 2021, most recently serving as a ticket and reservation supervisor, where he was recognized for his thoughtful leadership and commitment to the mountain. Reed has over 20 years of sales and marketing leadership experience…

CEDRR receives $2,500 Smart Growth Award

June 4, 2025
The Vermont Natural Resources Council announced the latest grant recipients for the Small Grants for Smart Growth program, May 27. Grantee selections are made on a rolling basis. The committee chose the Bridport Housing Task Force, the Chamber & Economic Development of the Rutland Region (CEDRR), and the South Burlington Energy Committee to be awarded a combined $6,750 in the most recent…

Big Brothers Big Sisters of Vermont celebrates 50 years of mentorship and community impact

June 4, 2025
2025 marks a significant milestone for Big Brothers Big Sisters of Vermont (BBBSVT), which is celebrating 50 years of empowering youth through meaningful, one-on-one mentoring relationships across the Green Mountain State. Founded in 1975 through Youth Services, BBBSVT has matched thousands of “Littles” with caring adult “Bigs,” fostering relationships that help young people realize their…

Motorized forage harvester falls into Hartland gorge

June 4, 2025
By Curt Peterson A convoy of haying equipment and workers started out from Braintree on Monday, May 26, to harvest 47 acres across from Harpoon Brewery for landowner John McGrail of Shepherds Brook Farms. Their journey was cut short when a 20-foot tall, 27-ton self-propelled John Deere forage harvesting machine, avoiding collision with an oncoming…