On June 28, 2017

Local roadwork continues

Work on local roads and bridges continues this week, causing some delays for travelers. Here is the latest travel update:

Route 4

Crews are scheduled to continue paving on milled surfaces and shoulder work  throughout this week.

Crews have also begun to pave driveway aprons on the Rutland Town/Mendon side of the project. This operation will be ongoing throughout this week and head east. Although driveway apron operations will be ongoing, they will not occur on a daily basis. This operation requires lane closures, and as a result, lane shifts and new traffic patterns will be in place throughout the construction zone. Please use caution when driving through the construction zone. Traffic control personnel will be onsite to assist with the flow of traffic.

The first half of the culvert on the Killington Flats has been set. Work during this week includes shifting traffic over to the westbound lane, and beginning excavation on the eastbound portion of the roadway to prepare for installation of the other half of the culvert. This work will require a one-lane alternating traffic pattern, and delays are expected throughout the week.

Route 73

Meanwhile in Rochester, Pike Industries continues planing activities towards the top of the gap, heading east toward Bingo Road and plans to be done later this week. Sections of Route 73 will be bare gravel following planing. Motorcycles and bicycles are encouraged to exercise extreme caution when traveling on milled or gravel road surfaces.

Reclaiming activities will begin this week at the Rochester/Goshen town line and will continue east toward the intersection of Bingo Road and Route 73. Pike will be hauling in gravel to construct roadways behind the reclaim operation.

Paving began last week at the intersection of Bingo Road and Route 73 and is moving east towards the intersection of Route 73 and Route 100. Pike will then start paving the intermediate course from the intersection with Route100 and move towards the intersection with Bingo Road on Route 73. The final lift of pavement will be placed when the remaining highway related construction is complete. Safety markings have been placed on cold planed and paved areas.

Bridge construction

The 35-day closure of Bridge 25 on Route 103 over the Black River in Ludlow remains in effect until July 15. Crews have finished driving piles and constructing the foundation of the new bridge. Night and weekend work is anticipated for this week.

Work on Bridge 99 on Route 100 in Ludlow is nearly completed. Crews will be intermittently working in the area of Route 100 Bridge 99 to complete punch list items.Traffic may be intermittently reduced to one lane with alternating one-way traffic at times during the remaining work. No night or weekend work is scheduled.

Do you want to submit feedback to the editor?

Send Us An Email!

Related Posts

Killington 1970s skiers reunite at Charity’s 1887 Saloon to celebrate lifelong memories, adventures, and cherished friendships at Charity’s 1887 Saloon

October 17, 2024
By Victoria Gaither Saturday, Oct. 19, at 2 p.m.—KILLINGTON— Charity’s 1887 Saloon will be the scene for the Killington 1970s Reunion social event. The event came about after organizer Jack Oliver attended his 50th high school reunion. Oliver explained, “I had never attended one before and was always reluctant to do so but enjoyed it.”…

Vermont Adaptive Ski and Sports seeks winter volunteer-instructors

October 17, 2024
Instructor training begins in November for skiing, snowboarding and winter sports KILLINGTON — Vermont Adaptive Ski and Sports, the largest year-round disabled sports nonprofit organization in Vermont to offer daily, year-round sports and recreation for people with disabilities, is looking for energetic winter volunteer-instructors who have a dedicated passion for sports and who want to…

Enter to win the 2025 Vermont Writers’ Prize

October 17, 2024
Annual prizes for poetry and prose celebrating Vermont are awarded by Green Mountain Power and Vermont Magazine. Winning entries in each category are published in the summer issue of Vermont Magazine and receive $1,250. The deadline to enter is Jan. 1, 2025. Entries are open for the 2025 Vermont Writers’ Prize, awarded each year in…

There’s no place like the stage: twists, turns, and punchlines from Vermont to Hollywood and back again – Nick Wevursky explains

October 17, 2024
Nick Wevursky, a standup comic in Rutland County, has always had a talent for finding humor in everyday life. Growing up across small towns in the Green Mountain state, he balanced activities like tending horse farms and snowboarding at Stratton, where his sister was a pro. Even as a kid, he loved making people laugh,…