More drainage, paving construction to come

By Evan Johnson

Roadwork continues on many well-traveled roadways in central Vermont this week. Here are updates on two projects causing the greatest delays in Killington and Rochester.

Route 73

Pike Industries and their subcontractor, J. Hutchins, will continue installing underdrain from the intersection of Route 73 and Clay Hill Road, moving towards Mom and Pop’s Sugar House. The majority of this work activity is planned to be complete by the middle of next week. The fine grading of the underdrain trenches to original grade will not occur until the end of project work.

This week Farquharson Brothers will begin construction and stabilizing stone slopes to match the proposed roadway profile. This work will begin at the top of the mountain, and work activities will move east.

Subcontractor Vermont Recreational Surfacing and Fencing will begin removing old guardrail and installing new guardrail as a barrier for temporary traffic protection while reclaiming the roadway. The contractor is planning to work Monday through Friday, 7 a.m.-5 p.m.

No roadway closures are expected as part of this project.

Route 4

Crews are scheduled to continue milling the road surface throughout this week. The milling operation is currently in the Killington area and moving east toward River Road.

Two way traffic will be maintained much of the time; however, stopped traffic and delays will occur intermittently, VTrans noted.

Photo courtesy of Jacqueline Dagesse
Springtime construction work continues on Route 73 in the area around Rochester.

Do you want to submit feedback to the editor?

Send Us An Email!

Related Posts

Officials strongly recommend limiting time outdoors in high-risk areas due to EEE threat

September 4, 2024
High-risk towns include Alburgh, Burlington, Colchester and Swanton  Health officials began strongly recommending people in towns at high risk for eastern equine encephalitis (EEE) avoid spending time outdoors as much as possible between 6 p.m. and 6 a.m. to avoid mosquitoes that could carry the virus, according to a Aug. 26 news release. If going…

Where is the state road construction? 

September 4, 2024
The Vermont Agency of Transportation (VTrans) published its weekly report of planned construction activities that will impact traffic on state highways and interstates throughout Vermont, Sept. 3-6 and ongoing. I-89 Royalton: Work continues on the northbound and southbound I-89 bridges near Exit 3 in Royalton. A new traffic pattern is in effect until fall 2025:…

Michael Costa named CEO at Gifford

September 4, 2024
Michael Costa will join Gifford Health Care as president and chief executive officer on Oct. 14, Gifford’s board of directors announced Aug. 29. Costa will succeed Dan Bennett, who will retire from the role at the Randolph hospital on Oct. 11. “Michael is a great fit for Gifford and our supportive, community-focused culture,” said Gifford…

Killington  Resort and Pico Mountain honor employees at annual Milestone Party

September 4, 2024
By Brooke Geery, Killington Resort Each year, Killington Resort celebrates its team members who have reached significant five-year milestones in their careers at The Beast. A party is thrown, complete with gifts from Yeti, a delicious steak dinner from Southside Steakhouse and an evening of fun and games at Stonehedge Indoor Golf. The 2024 gala,…