Roadwork: expect lane closures, milling, paving

Route 73

Pike Industries’ subcontractor, J. Hutchins, will continue replacing drainage culverts through this week. They will be working near the intersection of Route 73 and West Hill Road and moving west on Route 73. J. Hutchins will also be cutting brush that is overhanging the roadway next week. Pike Industries will install underdrain along Route 73, beginning near the intersection of Route 73 and Route 100 and moving west to the intersection of Route 73 and Bingo Road.

The contractor is planning to work Monday through Friday, 7 a.m.-7 p.m. There is alternating, one-way traffic around construction activities.

Route 4

Meanwhile, construction continues on the 15 miles of Route 4 between Mendon and Killington. Crews are scheduled to continue milling the road surface throughout the week of May 15. The milling operation is currently in the area of the Cortina Inn and moving easterly. It is possible that milling will reach the top of Sherburne Pass in the early part of the week of May 15. Two way traffic will be maintained much of the time; however, stopped traffic and delays will occur intermittently. Drivers are advised to plan their travel time accordingly.

Paving operations will continue to follow about four to six days behind milling operations. Crews are scheduled to continue paving in base course on milled surfaces throughout the week of May 15, weather permitting. By the end of this week paving crews will be in the vicinity of Sugar and Spice and possibly as far east as Wheelerville Road.

Drainage, milling and paving operations will require lane closures in the location of these operations. One eastbound lane and one westbound lane will remain open to traffic throughout the lane shift. One-way alternating traffic may be necessary for brief periods in order to maneuver construction vehicles and equipment.

Drivers are reminded to observe all signs, stay alert for flaggers and moving equipment, slow down, and exercise patience.

Do you want to submit feedback to the editor?

Send Us An Email!

Related Posts

Killington water tank on Shagback Mountain takes shape

July 2, 2025
The walls are up on Killington’s new water tank on Shagback Mountain. When completed it’ll stand 35-40 feet tall including the dome, with 4-6 feet buried underground. The walls were cast and lifted into place last week by Preload, a company specializing in building prestressed concrete tanks onsite. A crew is here from Texas to…

CEDRR receives $2,500 Smart Growth Award

June 4, 2025
The Vermont Natural Resources Council announced the latest grant recipients for the Small Grants for Smart Growth program, May 27. Grantee selections are made on a rolling basis. The committee chose the Bridport Housing Task Force, the Chamber & Economic Development of the Rutland Region (CEDRR), and the South Burlington Energy Committee to be awarded a combined $6,750 in the most recent…

Public notice: East Mountain Road Paving postponed till Tuesday, May 27.

May 23, 2025
KILLINGTON—Temporary paving of East Mountain Road is delayed due to weather until Tuesday, May 27. The area will remain gravel until then, and is open to all traffic.  Please get in touch with the Killington Public Works Director, Abbie Sherman, at 802-712-4243 or [email protected] with any questions or concerns.

Stafford Technical Center students construct planter boxes for Castleton seniors in time for spring planting

May 21, 2025
Stafford Technical Center students Tyler Gugliotta (left), Charlie Souza (middle), and Paden Lynch (right), as well as staff in the RHS EPIC After School Program Carpentry Club, constructed seven new planter boxes for the Castleton Community Seniors Wellness Center entrance.