On August 21, 2024
Uncategorized

Full Quechee Road rehab estimated at $6 million, options considered

Submitted

By Curt Peterson

Perhaps because of traffic volume on Quechee Road, and although there are much worse and less-used Hartland roads, conditions on the main route from Hartland Three Corners to Quechee village is the topic of frequent complaints on the local listserv.

The section between Gilson Road and Webster Road is particularly bad, featuring cracks, potholes, large patches of missing asphalt layers and failing road edges. For some years the common refrain has been “poor base that has to be replaced.”

At Monday’s Select Board meeting Scott Williams of Pathways Consulting in Lebanon reviewed a current eight-page engineering report regarding a detailed study of the 6-mile road that was financed with American Rescue Plan Act (ARPA) funds. The tests and engineering were performed by M&W Soils Engineering of Charlestown, and the report authored by Randal Rhodes.

Williams described how the engineers drilled approximately 40 holes 2-3 inches in diameter and up to 21/2 feet deep that took soil samples from the actual roadbed. The soil was then analyzed for components in a laboratory.

What they found was multiple layers of asphalt over a sub-base of gravelly sand from 18  inches to 30 inches deep, originally meant as base for a gravel road. “Movement” within this layer causes cracking in the road surface. When ruts are formed and overlaid with asphalt, Williams said, they remain as non-conforming parts of the base, exacerbating the movement and cracking effect.

“The overlayment on this road is actually in good condition,” he said. “It’s what’s underneath that’s causing the problem.”

The problematic section of Quechee Road has ledge on one side, and a steep slope on the other. Williams said inadequate ditching, ponding of water on the road, and subsidence on the slope side are also factors in the obvious surface failure.

He offered four options the town might use on the road.

Option 1: just to do another 1- to 11/-inch layer of asphalt paving over the entire road.

Option 2: involved “inlay and overlay,” milling the road surface to assist in bonding the new application to the existing road surface.

Option 3: remove and reclaim the existing base and overlay before replacing, adding 4 inches of gravel or crushed stone and overlaying with new asphalt.  “This option would not be very effective for the bad areas,” Williams said.

Option 4: Excavate 18 inches (maybe 24 inches) of material and replace with appropriate sub-grade and sub-base component before overlaying with new asphalt. “This will be very expensive,” Williams said. “But if you consider your current ongoing and repetitive costs, you will save money in the long term.”

His rough estimate for Option 4 was $1 million per mile, or $6 million total, including a 20% contingency for unexpected issues.

Williams recommends doing the entire road, or at least significant sections, rather than limiting the project to the bad areas, as contractor costs for multiple smaller jobs will be higher.

“The contractor will probably execute the work one lane at a time, for minimum traffic disruption,” he said.

The culverts that were inspected are also in bad shape — some clogged, about 30% rusted through. These issues and some guardrail damage would be mitigated separately, by the town.

Williams offered his help when the town begins planning and budgeting for the work.

Do you want to submit feedback to the editor?

Send Us An Email!

Related Posts

VTSU names John Casella 2025 Castleton commencement speaker

April 23, 2025
Vermont State University (VTSU) is graduating its second class this spring on May 17-18, 2025 and has announced a remarkable lineup of commencement speakers for the four ceremonies, held at the Castleton, Lyndon, Johnson, and Randolph campuses over the weekend.  “We are delighted to welcome distinguished alumni and campus community leaders John Casella, Greg Tatro,…

Rutland affordable housing project earns state award for energy excellence

April 23, 2025
RUTLAND— A historic home on River Street in Rutland has been recognized among Vermont’s top energy-efficient building projects, earning a “Best of the Best” award at Efficiency Vermont’s annual Better Building by Design (BBD) conference. The award, presented to Hildebrand Homes, LLC, highlights a creative and forward-thinking approach to affordable housing that aligns energy efficiency…

Youth turkey-calling contest draws record participation

April 23, 2025
CASTLETON— A record-breaking 33 young participants, ranging in age from 2 to 18, showcased their best gobbles, clucks, and yelps at the 19th annual Bart Jacob Memorial Youth Turkey Calling Contest on April 12 at Kehoe Conservation Camp in Castleton. Sponsored by the Oxbow Mountain 4-H Club and underwritten by the Vermont Fish and Wildlife…

How Killington became The Beast: Part 7

April 23, 2025
By Karen D. Lorentz Editors’ Note: This is part of a series on the factors that enabled Killington to become The Beast of the East. Quotations are from author interviews in the 1980s for the book “Killington, A Story of Mountains and Men.” Despite the two-year delay to Killington’s debut—caused by the access road not…