On June 12, 2024
Local News

Killington road work extends into Saturday morning

By Pat Wise - Construction continues at the base of Killington Road where it intersects with Route 4.

Drilling and blasting will continue this week at the intersection of Route 4 and Killington Road in Killington. A detour remains in place via West Hill Road. 

As the project approaches the scheduled end date of July 8, work to haul out rock will occur on Saturdays till about noon time going forward, Markowski Excavating, Inc. explained.

“Although the second drill rig was supposed to arrive last week, it will be on site either Monday or Tuesday. [We] expect delivery of the drill and another delivery of blasting matts to arrive either of these days,” Markowski continued in a update in advance of this week’s roadwork. “They will start drilling down near Route 4, then work up the east side of the access road to remove remaining ledge. Due to timing, there may be multiple blasts per day if it lines up. Traffic will be stopped for those shots, so be aware of flaggers on the road to stop vehicles for 5-10 minutes.”

Otherwise, as has been the case for the past month, there’ll be one blast daily between 11 a.m. and 12-noon, “but if there is any unforeseen delays it could be as late as 1 p.m.,” Markowski noted.

Work this week will focus on installing the sewer structures and pipe along Route 4. 

“We will then focus the second half of the week on installing water and sewer line away from Route 4 south on the Access Road. As this progresses, expect more sand and gravels to be installed to build up the road base,” Markowski noted.

Work for the following week, beginning June 17, will be a continuation of drilling and blasting rock with dump trucks entering and exiting the site to load out rock.

Sewer line installation will continue to be installed up the east side of Killington Road. 

“In addition, we will be also working to install the future water line along the west side of the Access Road. Again, as these two lines are installed, we will continue to install the sand and gravel layers which will be just below final pavement layer,” Markowski noted.

A continuation of dust control will occur as needed with warmer and drier weather.

Do you want to submit feedback to the editor?

Send Us An Email!

Related Posts

KPAA honors Brett Harris with Killington 

December 18, 2024
Pico Area Association’s Outstanding  Community Member of the Year On Thursday, Dec. 5, Brett Harris received the honor of Killington Pico Area Association’s (KPAA) Outstanding Community Member of the Year. Whether attending fundraisers, cheering on the Steelers at Jax’s, or spreading smiles at local events, KPAA recognized Harris’ inspiring dedication. Harris’s passion was even the…

Latin-inspired flavors hit Rutland

December 18, 2024
By James Kent There is exciting news in the culinary world. The Rutland area has two new eating destinations with Latin-inspired flavors that will expand palates and stuff tummies with delicious treats from regions such as Peru, Venezuela, and Argentina.  Pao Pao is a Peruvian restaurant that opened on Dec. 6 at 124 Woodstock Ave.…

Social Tinkering’s annual Light Up Rutland County event

December 18, 2024
It’s time to go light-peeping! The Light Up Rutland County winter lights and decorating contest is in full swing, with nine competing households, two non-competing households, and a local business decorator all ready for visitors to come see their lights. Videos and slideshows for school decorators will be posted on Social Tinkering’s website after Dec.…

Okemo Valley Holiday Express brings festive cheer to Vermont

December 18, 2024
Dec. 21 through 22 from 9 a.m to 6 p.m.—CHESTER—The Okemo Valley Regional Chamber of Commerce (OVRCC), in collaboration with Vermont Rail System, is launching the Okemo Valley Holiday Express, a new festive holiday train experience for families and visitors. Running on Dec 21 and 22, the excursion train offers a scenic journey through South-Central…