State auditor revisits dam safety

Killington’s Kent Pond Dam listed in top 10 with significant hazard potential 

Staff report

“When nine inches of rain falls in a short period of time, bad things are going to happen. It’s not always clear what those bad things will be, but we know some communities will flood, some infrastructure will be damaged, and some lives will be impacted,” wrote Vermont Auditor Doug Hoffer whose office audited the performance of Vermont’s Dam Safety Program (DSP) before July and August’s flooding events. 

“Government can proactively take steps to mitigate the risks or severity of disasters, though, especially in terms of critical infrastructure, Hoffer continued. “Unfortunately… prevention is often underfunded and unappreciated.”

The DSP audit questions whether Vermont was doing all it could to make sure Vermont’s hundreds of dams are being inspected frequently enough, and whether they were being properly maintained to keep people safe.
Here’s what he found: “Overall, we found that the Dam Safety Program had historically been too understaffed to fulfill its inspection duties, that many large dams were allowed to linger in poor condition for many years (including some state-owned dams), and that new rules intended to require improvements where life and property is threatened are well more than a year behind schedule,” he wrote. Specifically:

The DSP has not been inspecting all dams within the required timeframe and has not recorded all inspections in their inventory database.

The DSP’s centralized dam inventory does not include complete and accurate condition and hazard potential ratings.

Although, the DSP followed up on the recommendations they made to dam owners during inspection visits during subsequent inspections, in most cases, the subsequent inspections found that the dam owners had taken little or no action to improve the overall condition of the dam.

Some of the dams in the review had been classified as being in poor condition for as much as 18 years, shown in the table above.

“As we finalized our audit, the Administration proposed, and the Legislature approved, the addition of several new staff positions at the Dam Safety Program and a one-time boost in funds to carry out more dam assessments,” Hoffer continued. “These are positive developments, but more is needed… Vermont state government knows that a number of large dams are in bad shape, and that if they fail Vermonters could be killed or significant property damage could occur. For too long, state officials have demurred on prioritizing the funds and policies needed to safeguard against catastrophes.

“In light of this summer’s floods, and knowing full well that these rain events are going to come ever more frequently, perhaps now this critical and dangerous infrastructure will receive the preventive care that’s needed,” Hoffer concluded.

Do you want to submit feedback to the editor?

Send Us An Email!

Related Posts

Superstar Six-Pack construction hits new phase as helicopters fly in concrete

July 3, 2025
KILLINGTON — Construction of the new Superstar six-pack chairlift has reached an exciting phase this summer, with helicopters now flying in concrete for the tower and terminal footings. On Wednesday, July 1, a helicopter was seen flying to Killington Resort with a payload of concrete. Killington Resort is replacing its iconic Superstar Express quad with…

Local road construction plans for 4th of July week

July 2, 2025
The following is a weekly report that lists its planned construction activities that will affect traffic on state highways and interstates throughout Vermont for the week of June 30. Most construction projects will pause work for the 4th of July `Local roads in Rutland and Windsor County, include:     I-89 Royalton Construction continues Monday through…

Ribbon cuttings in Ludlow and Proctorsville highlight local business growth

July 2, 2025
A pair of ribbon cuttings on June 20 held by the Okemo Valley Regional Chamber of Commerce (OVRCC) marked a day of celebration for two local businesses and offered a boost of momentum to the region’s small business economy. In Ludlow, Aubuchon ACE Hardware unveiled its newly renovated store on Main Street with a grand…

Cirque Series celebrates successful Killington debut

July 2, 2025
By Polly Mikula The Cirque Series broke trail in New England with two new races. On June 7, runners raced up Cannon Mountain in Franconia, New Hampshire and this past Saturday, June 28, they tackled “The Beast of the East,” Killington Mountain. Cirque is also adding Crystal Mountain, Washington, to its national lineup of eight…