On August 9, 2023

Hartland intersection redo hits design snag

 

By Curt Peterson

Four members of the Hartland Select Board grilled Daniel Peck, project manager for Vanasse Hangen Brustlin (VHB) engineers, regarding three expensive glitches discovered during the now-notorious $1.5 million intersection reconfiguration in Hartland Three Corners.

Board Chair Phil Hobbie outlined the issues, including failure to provide replacement street lighting in the project plans, failure to contemplate a layer of highway concrete under a proposed tree-planting area, and some drainage design issues the board feels should have been obvious.

“These are expensive issues,” Hobbie said, “and we need to resolve them so our taxpayers aren’t penalized for any engineering design errors.”

Design plans called for removing two light-bearing utility poles as part of installing underground utilities, but no consideration was given in the plans for replacing the lighting.  Hobbie said the cost of rectifying the mistake will be between $75,000 and $100,000.

The green area meant to be where the “triangle” was between Routes 12 and 5 to receive tree plantings that would require at least 24” of clean soil for their roots. Apparently VHB didn’t contemplate the cost of removing 5” of highway concrete so the trees could be planted. Hobbie said the cost of this glitch will be $25,000.

There is no cost estimate for correcting a design flaw that causes “pooling” of rainwater where the new and old sidewalks meet, a problem that the Select Board also considers a VHB failure.

Hobbie asked Peck question after question, laying the groundwork for the town’s opinion that VHB should be responsible for rectification.

“None of us are engineers,” Hobbie said to Peck. “We relied on VHB to provide the expertise that should have prevented these problems.”

Selectman Tom Kennedy said he’s known David Saladino, the managing director of VHB’s division that is involved in the Hartland project, for years, and feels “Saladino should call our board chair and find the solution to these problems.”

The cost of the lighting issue will be mitigated by a suggestion from GPI, the on-site engineers for the project, Hobbie said. The necessary wiring for any new lights will be buried with the other utilities, and can be accessed without re-excavating to place them underground. There are also lighting design suggestions, all of which will require state approval before they can be installed.

Asked if he thinks any or all of these issues might cause a delay in completing the reconfiguration project, Hobbie said, “No.”

Do you want to submit feedback to the editor?

Send Us An Email!

Related Posts

Robert Hecker appointed to Killington Select Board

May 15, 2024
By Curt Peterson Robert Hecker has been appointed to take Steve Finneron’s seat on the Killington Select Board. The announcement came after an executive session Monday night May 13. The position lasts until next Town Meeting Day vote, when voters will choose the person to fulfill the remaining year of Finneron’s term.  Hecker was one…

Town resolves eminent domain 

May 15, 2024
Deal with landowner called ‘win-win’ By Polly Mikula The town of Killington will not pursue an eminent domain hearing scheduled for May 20, having recently resolved the case with the landowner.  Eva Nagymihaly and her sister, Theresa Rust, own land on the east side at the base of Killington Road to the intersection with Route…

Logging company fined for wetland and water quality impacts in Bridgewater, Thetford

May 15, 2024
The Agency of Natural Resources Dept. of Environmental Conservation (DEC) and Vermont Forests, Parks, and Recreation (FPR) announced May 8 that Thomson Timber Harvesting and Trucking LLC (Thompson Timber), a company that performs logging activities in Vermont, was fined $32,550 for violating the Vermont Wetland Rules and failing to follow acceptable management practices (AMPs) for…

Wonderfeet Kids’ Museum celebrates expansion

May 15, 2024
By Polly Mikula Saturday, May 11, Wonderfeet Kids’ Museum held a grand opening celebration from 10 a.m.-2 p.m. on Merchants Row downtown. While the museum relocated to its current location (66 Merchants Row) last spring, this was the first time the organization has celebrated that expansion. The move allowed Wonderfeet Kids’ Museum to tripled in size with new…