On June 14, 2023

$2.25M Hartland intersection reconfiguration begins

 

By Curt Peterson

Monday, June 12, will go down in Hartland history as a momentous occasion, as Nott’s Excavating, winner of the project bid, started unloading a considerable armada of heavy equipment for reconfiguring the intersection of Quechee Road and state Routes 5 and 12. It took a decade to get to this point. The project is scheduled for completion by this September.

Hartland Three Corners, everyone agrees, will never be quite the same once actual digging begins near Mike’s Store on 5/12 North. A controversial project from its beginning, some residents are still unsure how it ever happened, what it’s all about, and how the finished project will appear and function.

As recently as Tuesday, June 13, one listserv poster thought reconfiguration meant a rotary, something that has never been considered.

Rita Seto, senior planner at Two Rivers Ottauquechee Regional Commission (TRORC), presented “A Project History” at the June 5 selectboard meeting, which was meant to dispel misinformation and conspiracy theories surrounding the project. Unfortunately, the informational meeting was sparsely attended.

The project has always been about safety, of course, with considerations for cost and aesthetics. Strong opinions, both pro and con, are rooted in one or more of these issues.

TRORC has been instrumental in making the project a reality, assisting grant capturing, arranging scoping studies and overseeing progress, while town selectmen have come and gone. Not one of the current selectmen was also serving in 2013 when the project was an idea, and VTrans awarded Hartland a Transportation Enhancement scoping grant.

A study researched what changes at the intersection would best enhance bicycle and pedestrian safety. A four-way configuration was deemed best.

A frequently cited near-tragic incident involving a toddler crossing the intersection and a large truck barreling around the blind curve on Route 5 brings chills. However, VTrans records show there has never been a recorded major accident at the site.

In 2015 the Select Board engaged engineering firm VHB to design the new configuration, resulting in an estimated construction cost of a little more than $500,000 using town funds.

In 2017 the state committed almost $100,000 to pave a portion of Quechee Road as part of the project.

Two years later a bike ped grant for $269,600 was awarded for funding sidewalk enhancement as part of the design. 

The Select Board decided in 2020 to begin construction work 2021. An additional $125,000 grant was received to cover unanticipated additional costs for sidewalk construction. Also that year, Hartland voters approved the intersection design, including burial of utilities for aesthetic reasons, and authorized a bond for $1,062,000. The bond proceeds were in addition to grants received for the project.

But 2021 found stakeholders, including TRORC, struggling to coordinate five utilities regarding general construction and specifically, burying the utility lines.

Selectmen solicited bids for the project in 2022 at an state-produced estimated cost of $929,433, but there was only one bid — for $1,497,530 — which was rejected. 

An independent cost estimate was arranged.

In 2023, the projected cost for the reconfiguration is $1,248,853. Nott’s Excavating was awarded the contract at about $35,000 over the estimate.

Besides the cited poster’s confusion about the traffic pattern, the listserv is peppered with suggestions for renaming the village center. One example: “Hartland’s Folly.”

Old Home Day fans need not worry — the intersection will be wide open for the parade and the crowds, according to the Select Board.===

Do you want to submit feedback to the editor?

Send Us An Email!

Related Posts

Local road construction plans for 4th of July week

July 2, 2025
The following is a weekly report that lists its planned construction activities that will affect traffic on state highways and interstates throughout Vermont for the week of June 30. Most construction projects will pause work for the 4th of July `Local roads in Rutland and Windsor County, include:     I-89 Royalton Construction continues Monday through…

Ribbon cuttings in Ludlow and Proctorsville highlight local business growth

July 2, 2025
A pair of ribbon cuttings on June 20 held by the Okemo Valley Regional Chamber of Commerce (OVRCC) marked a day of celebration for two local businesses and offered a boost of momentum to the region’s small business economy. In Ludlow, Aubuchon ACE Hardware unveiled its newly renovated store on Main Street with a grand…

Cirque Series celebrates successful Killington debut

July 2, 2025
By Polly Mikula The Cirque Series broke trail in New England with two new races. On June 7, runners raced up Cannon Mountain in Franconia, New Hampshire and this past Saturday, June 28, they tackled “The Beast of the East,” Killington Mountain. Cirque is also adding Crystal Mountain, Washington, to its national lineup of eight…

Rutland Sculpture Trail announces 14th installation

July 2, 2025
The 14th addition to the Rutland Sculpture Trail will honor the community’s giving spirit, volunteerism, and inspiration - and the national record for donating blood. Organizers have commissioned a piece honoring Rutland’s Gift-of-Life Marathon (GOLM), which still holds the one-day U.S. record for blood donations 12 years after setting the record and continues to inspire…