On December 22, 2022

Killington to remove beaver dams

By Katy Savage

Killington is removing beaver dams to stop stormwater runoff and protect infrastructure.

The town was granted a stream alteration permit from the Agency of Natural Resources (ANR) on Nov. 23  to remove and downsize five beaver dams in a 6.1-mile stretch along the Ottauquechee River corridor.

“The town of Killington has a history of beaver problems within the Ottauquechee River corridor,” according to the permit application. “While the town has historically managed the beavers through periodic trapping, in recent years dam construction has resulted in overtopping of town culverts and bridges, flooding of roadways, and damage to private and public property.”

Dams are approximately 1 1/2 to 2 feet higher than normal water surface. Town Manager Chet Hagenbarh said seven culverts have backed up in recent storms, causing road damage.

“Over the last three years, it made a lake out of the place,” he said. “There was no place for stormwater to go and created big storm risks.”

The removal of dams has been controversial in the past. In September 2019, the town received an ANR compliance visit after a resident complained the town was removing beavers and dams illegally and without state permission.

John Keough, who filed the complaint in 2019, said he benefits from the beavers and kayaks on the river for his business Appalachian Trail Adventures, Inc. “Killington refuses to follow DEC guidelines and to install baffles,” Keough said in a 2019 letter to the editor published in the Mountain Times. “They just removed the dams, causing the beavers to cut down more trees and brush to rebuild the dam. Thus, causing bank erosion, poor water quality, poor fish habitat and destruction to private property.”

Both Hagenbarth and the ANR determined at that time that the town had a right to remove beaver dams to protect public and private infrastructure.

This time, Keough questions the financial ramifications of removing the dams.

“I keep saying the same thing, they keep removing the beaver dams and trapping them and they keep coming back,” he said. “You’re getting nowhere.”

The town hired Mosher Excavating to resume the dam removal process in the spring. Hagenbarth said he was using money from the highway budget. He wasn’t sure how much it would cost.

“There are certain rules that apply when you can remove them,” he said. “Some people think you’re not supposed to touch them. That’s not the case, you’re supposed to manage them.”

ANR visited Kililngton in November 2020 and December 2021. The permit allows the town to remove up to a foot of water per day.

“Due to ample flood storage in the wetlands along this corridor this reduction is not anticipated to result in undue adverse impact,” the permit said

Hagenbarth said the water level has been reduced by at least a foot so far. “It’s allowing nature to do what it’s going to do without dramatically impacting the town’s infrastructure,” Hagenbarth said.

Do you want to submit feedback to the editor?

Send Us An Email!

Related Posts

Pride in Rutland: Flags, resistance, and showing up

June 25, 2025
By Emily Pratt Slatin Pride returned to downtown Rutland this June with more color, noise, and purpose than ever before. What began as a joyful celebration quickly became something deeper—something that felt like resistance. And belonging. And a promise that no one in this community has to stand alone. The day kicked off with the…

Plan to manage 72,000 acres of the Telephone Gap project is finalized

June 25, 2025
Staff report The U.S. Forest Service issued its final plan for managing 72,000 acres of public and private land on June 16. The proposed Telephone Gap Integrated Resource Project area is located on the Green Mountain National Forest (GMNF) within the towns of Brandon, Chittenden, Goshen, Killington, Mendon, Pittsfield, Pittsford, and Stockbridge. “The Telephone Gap project is…

Hot air balloons took flight over Quechee

June 25, 2025
By James Kent This past weekend, June 21-22, people came from all over New England to participate in the 45th annual Hot Air Balloon Festival. Music, food, games, and fun were available for all ages throughout the weekend, but the main attraction was the hot air balloons. And for those looking to see these gigantic,…

Killington residents push for skate park as town reimagines recreation future 

June 25, 2025
By Greta Solsaa/VTDigger As Killington celebrates the 50th anniversary of its recreation center, some residents are pushing to make a skate park a new permanent fixture of the town’s summer offerings.  The town crafted its recreation master plan to holistically determine how to best use its resources to serve residents in the future, Recreation Department Director Emily Hudson…