KES to get new $2M roof

By Katy Savage

Killington Elementary School is slated to get a new roof next year.

The building’s roof is “leaking everywhere,” Jim Fenn, Windsor Central Supervisory Union’s director of finance and operations, told board members on July 12.

The project is estimated to cost up to $2 million for a new roof and insulation inside the building. Fenn said an architect is addressing the roof issues of the school, which dates back to the 1970s.

By Polly Mikula
Killington Elementary School will get new $2 million roof.

Joe Rigoli, the district’s buildings and grounds manager, said the contractors will likely build a new metal standing seam roof or an asphalt roof over the top of the existing roof.

“The school has massive heat loss coming out through the roof itself,” he said after the meeting.

Rigoli said the European-style roof is a “cold roof,” built to hold snow on top of it as insulation. Cold roofs are meant to prevent ice dams and leaks.

“What happens is the complete opposite,” Rigoli said, explaining there weren’t sufficient engineering studies done when the building was constructed.

Giant icicles form on the roof in the winter and “literally touch the ground,” he said, forming hazards for people walking by.

“In the winter it really does wreak havoc,” Rigoli said.

The project will be out to bid in January and upgraded next summer. At the same time, the board will put out a bid construction of a new $1 million heating system at Woodstock Union High School.

The School Board approved a $75,000 expense on July 12 so Dubois & King Inc. can complete an engineering study for a new heating system in addition to a $20,000 expense to band-aid the existing system this winter.

Rigoli said the high school portion of the 1950s building runs on steam.

“There’s just no repairing it anymore,” he said after the meeting. “There’s really not much more we can do. It was a daily struggle even to moderate the temperature in the building. Things are so old, they don’t function well.”

The $20,000 tune-up to replace gaskets and rebuild some pumps will be done before the next school year begins. Rigoli hopes to change the steam system to hot water and have a bid out in January to complete the work next summer.

Board members at the meeting discussed the pros and cons of replacing the heating system while they anticipate a new $80 million high school and middle school building in the not-too-distant future.

Some have questioned if the upgraded heating system could be used in the new building but the board has yet to decide what the new heat system will be in the new building and several board members emphasized the dire need to replace the heating system before it fails.

“If there’s anything that keeps me up at night, it’s not Covid anymore, it’s what’s going to be happening to that building,” Superintendent Sherry Sousa said.

The School Board’s buildings and grounds committee looked into using external classrooms, leasing another facility, and using heat pumps at the existing building before determining that converting the steam system to hot water was the least costly solution.

“We did our homework,” said board member Jim Haff.

Do you want to submit feedback to the editor?

Send Us An Email!

Related Posts

Robert Hecker appointed to Killington Select Board

May 15, 2024
By Curt Peterson Robert Hecker has been appointed to take Steve Finneron’s seat on the Killington Select Board. The announcement came after an executive session Monday night May 13. The position lasts until next Town Meeting Day vote, when voters will choose the person to fulfill the remaining year of Finneron’s term.  Hecker was one…

Town resolves eminent domain 

May 15, 2024
Deal with landowner called ‘win-win’ By Polly Mikula The town of Killington will not pursue an eminent domain hearing scheduled for May 20, having recently resolved the case with the landowner.  Eva Nagymihaly and her sister, Theresa Rust, own land on the east side at the base of Killington Road to the intersection with Route…

Logging company fined for wetland and water quality impacts in Bridgewater, Thetford

May 15, 2024
The Agency of Natural Resources Dept. of Environmental Conservation (DEC) and Vermont Forests, Parks, and Recreation (FPR) announced May 8 that Thomson Timber Harvesting and Trucking LLC (Thompson Timber), a company that performs logging activities in Vermont, was fined $32,550 for violating the Vermont Wetland Rules and failing to follow acceptable management practices (AMPs) for…

Wonderfeet Kids’ Museum celebrates expansion

May 15, 2024
By Polly Mikula Saturday, May 11, Wonderfeet Kids’ Museum held a grand opening celebration from 10 a.m.-2 p.m. on Merchants Row downtown. While the museum relocated to its current location (66 Merchants Row) last spring, this was the first time the organization has celebrated that expansion. The move allowed Wonderfeet Kids’ Museum to tripled in size with new…