On December 15, 2021

Okemo debuts two express lifts

By Karen D. Lorentz

Just as the mail gets delivered in rain, snow, hail and dark of night, the workers at Okemo Mountain Resort debuted the new Quantum Six Express chairlift as scheduled on Saturday, Dec. 11 — despite the unseasonable rain. After early morning haul line de-icing, the six-seat chairs were put on the cable to speed riders to the summit of Jackson Gore.

Riding up on the first chair with Okemo managers, I asked Vice President and General Manager Bruce Schmidt what the determining factor was to choose this replacement lift for the Quantum Four Express. Without hesitation he replied, “a 50% increase in lift capacity.”

Submitted
A team of Okemo lift workers made the debut of the new Quantum Six high speed chairlift happen as scheduled Saturday, Dec. 11, despite the rainy conditions.

That’s good news for weekend and holiday guests who often waited in line at the prior chair as they sought to access upper Jackson Gore trails or make their way to the main mountain or South Face areas.

“The lift capacity for the Quantum Six is rated at 2,900 rides per hour, based on optimal operating conditions,” Communications Manager Bonnie MacPherson said.

But the good news doesn’t end there as the (former) Quantum Four highspeed bubble lift was relocated to replace the Green Ridge Triple fixed grip chairlift and now offers an easier and quicker way to Okemo’s main summit. Renamed the Evergreen Summit Express, it debuted Dec. 4 and offers a four-minute ride versus the triple’s 8 minutes as well as 2,180 rides per hour versus the triple’s 1,800. It also offers the comfort of the bubble, a retractable transparent dome that skiers and snowboarders have the option to use for weather protection and warmth on windy, cold days.

“With the opening of the two lifts, Okemo has completed a transformational upgrade — part of a Vail Resorts capital improvement plan that makes accessing the mountain faster and easier. Okemo now has two bubble lifts that access the summit area and a second six-passenger lift,” MacPherson said.

Both lifts were manufactured by Leitner-Poma of America.

The major infrastructure improvements took place between April and November 2021 and also included terrain and snowmaking expansions. A key component to shortening the time to access the main summit for those approaching from Jackson Gore is the Green Link, a short new connector trail with snowmaking that leads from the intersection of Upper Mountain Road and Roundhouse Run to the base of the new Evergreen Summit Express.

Senior Director of Mountain Operations Eb Kinney noted the Evergreen lift offers a good alternative to the Sunburst Six for skiing a host of upper mountain trails like Timberline, Sapphire, Tomahawk, and Jolly Green Giant, several tree runs, and some easy greens. Greater usage of this underutilized lift/skiing area will reduce lift waits at the popular Sunburst Six, he added.

The lifts and trail upgrades will also cut the time to access the summit of South Face from Jackson Gore’s base from approximately 40 to 25 minutes.

Now in its 66th winter season, Okemo Mountain Resort is one of the most technologically advanced ski areas in the East with six express lifts and snowmaking capability on 98% of its trails.

Do you want to submit feedback to the editor?

Send Us An Email!

Related Posts

Pride in Rutland: Flags, resistance, and showing up

June 25, 2025
By Emily Pratt Slatin Pride returned to downtown Rutland this June with more color, noise, and purpose than ever before. What began as a joyful celebration quickly became something deeper—something that felt like resistance. And belonging. And a promise that no one in this community has to stand alone. The day kicked off with the…

Plan to manage 72,000 acres of the Telephone Gap project is finalized

June 25, 2025
Staff report The U.S. Forest Service issued its final plan for managing 72,000 acres of public and private land on June 16. The proposed Telephone Gap Integrated Resource Project area is located on the Green Mountain National Forest (GMNF) within the towns of Brandon, Chittenden, Goshen, Killington, Mendon, Pittsfield, Pittsford, and Stockbridge. “The Telephone Gap project is…

Hot air balloons took flight over Quechee

June 25, 2025
By James Kent This past weekend, June 21-22, people came from all over New England to participate in the 45th annual Hot Air Balloon Festival. Music, food, games, and fun were available for all ages throughout the weekend, but the main attraction was the hot air balloons. And for those looking to see these gigantic,…

Killington residents push for skate park as town reimagines recreation future 

June 25, 2025
By Greta Solsaa/VTDigger As Killington celebrates the 50th anniversary of its recreation center, some residents are pushing to make a skate park a new permanent fixture of the town’s summer offerings.  The town crafted its recreation master plan to holistically determine how to best use its resources to serve residents in the future, Recreation Department Director Emily Hudson…