On June 2, 2021

Killington Select Board engages TIF consultant

By Curt Peterson

The Killington Select Board unanimously authorized execution of a contract engaging White + Burke Real Estate Advisors, Inc. to shepherd the town’s application for approval of a tax increment financing (TIF) district, pending approval by the town’s legal counsel.

Approval as a TIF district would provide funding for infrastructure improvements that would trigger private development, raise tax revenues and create jobs.

Killington seeks funding for its Killington Road master plan (repaving and expanding) and a new municipal water system, which totals about $50 million. 

Under the TIF program, Killington would use 85% of the municipal increase from the TIF-district to pay debt service and 70% of the education fund to service debts.

The first of two contract phases will “determine the feasibility of a [TIF] district in Killington, and the community’s readiness for a TIF district,” according to White + Burke’s proposal, as well as review of “private development projects and related public infrastructure investments.”

White + Burke will then assess the “financial viability” of the proposed TIF project.

Generally, viability is determined by comparing the cost of infrastructure improvements necessary for TIF qualification, the cost of debt service regarding TIF bond financing, and anticipated TIF-increased tax revenue.

In Phase II, White + Burke would submit the official application for state approval. 

“This involves preparation and adoption of a written TIF plan that includes data analysis and explains the opportunities and implications for the town,” the proposal indicates, including informational meetings, any necessary hearings, and facilitating Select Board approval.

As cited, private investment is necessary to qualify for TIF funding. White + Burke will assist the town in negotiating with developers, who have not yet been publicly named. But because White + Burke has previously represented SP Land Company, which owns the development rights for the proposed TIF district, in their “planning and permitting on the Killington Village Master Plan project,” a resolution to avoid conflict of interest has been drafted. 

Town Manager Chet Hagenbarth and SP Land President Steven Selbo negotiated a “Mutual Agreement Regarding Retention of White + Burke Real Estate Advisors, Inc.” to resolve any conflict of interest, stating: “The Town and SP Land … agree that the Town’s use of [White + Burke] for [TIF] financing related representation will not prevent or inhibit any future representation by [White + Burke] on behalf of SP Land … with respect to its ongoing planning and permitting efforts.” The document was also signed by White + Burke Vice-President Stephanie Clarke in acknowledgement.

The White + Burke contract calls for “time and materials” billing, with an estimate of $20,000 for the first phase, and $30,000 for the second. This does not include fees for any specialists or consultants that White + Burke and the Select Board agree to engage.

Selectman Jim Haff, who made the motion to authorize the contract, said the $50,000 total estimated cost would be included in approved financing for the TIF project if the state ultimately approves Killington’s application.

“And if not approved,” he asked, “where would the funding come from?”

Hagenbarth said that the town could pay it out of the Killington Road master plan restricted fund with the road pavement portion. “In either case, the contract won’t affect the budget,” he said.

Clarke will be the project manager for Killington’s TIF quest. She has successfully shepherded six of the seven total TIF districts that have been approved by the state, including projects in Burlington, White River, St. Albans and Barre.

Do you want to submit feedback to the editor?

Send Us An Email!

Related Posts

Pride in Rutland: Flags, resistance, and showing up

June 25, 2025
By Emily Pratt Slatin Pride returned to downtown Rutland this June with more color, noise, and purpose than ever before. What began as a joyful celebration quickly became something deeper—something that felt like resistance. And belonging. And a promise that no one in this community has to stand alone. The day kicked off with the…

Plan to manage 72,000 acres of the Telephone Gap project is finalized

June 25, 2025
Staff report The U.S. Forest Service issued its final plan for managing 72,000 acres of public and private land on June 16. The proposed Telephone Gap Integrated Resource Project area is located on the Green Mountain National Forest (GMNF) within the towns of Brandon, Chittenden, Goshen, Killington, Mendon, Pittsfield, Pittsford, and Stockbridge. “The Telephone Gap project is…

Hot air balloons took flight over Quechee

June 25, 2025
By James Kent This past weekend, June 21-22, people came from all over New England to participate in the 45th annual Hot Air Balloon Festival. Music, food, games, and fun were available for all ages throughout the weekend, but the main attraction was the hot air balloons. And for those looking to see these gigantic,…

Killington residents push for skate park as town reimagines recreation future 

June 25, 2025
By Greta Solsaa/VTDigger As Killington celebrates the 50th anniversary of its recreation center, some residents are pushing to make a skate park a new permanent fixture of the town’s summer offerings.  The town crafted its recreation master plan to holistically determine how to best use its resources to serve residents in the future, Recreation Department Director Emily Hudson…