On November 4, 2020

Covid contributes to Killington’s Public Safety Building budget set-back

By Polly Mikula
An extra water tank costing $50,000 was installed at the Public Safety Building to meet state mandates for capacity.

By Curt Peterson

As first responders, including firemen, search and rescue and police, begin moving into Killington’s new Public Safety Building, the Select Board is sorting through final bills and funding.

At a special meeting on Oct. 27 Town Manager Chet Hagenbarth told selectmen project costs have exceeded the expectation by more than $400,000 for non-building surprises to date, that balance is after receiving at least $300,000 (the minimum bid) through the future sale of the existing Fire House.

A Request for Proposals (RFP) of purchase has been issued, and Haff said he has heard from some interested parties asking about acceptability of their plans for the building.

“As a board, we are not exercising discretion over who can occupy the building or for what purpose,” Haff said. “Any proposed use will have to be reviewed and approved by the zoning administrator.”

RFP are due by noon Nov. 6 and the Select Board anticipates reviewing the proposals at a meeting on Nov. 10.

“The Select Board intends to select the the proposal which provides the best value for the town,” according to the official RFP.

What added costs?

Early testing indicated minimum underground ledge issues, but as the project moved forward much was found. Unanticipated blasting has cost the town an additional $212,000 and ate up the construction clock.

The Covid-19 pandemic is to blame for some of the overrun, according to Hagenbarth. Pandemic-related delays threatened an additional four months’ interest cost, and $161,000 was invested in warming the ground and materials so work could move forward.

“Delays caused by the shut-down cost us $55,000,” he said. “We hope to be able to recoup $25,000 of that from Covid relief funds, and we may be able to get the entire $55,000.”

The well seemed more than adequate, producing 55 gallons/minute, but the Division of Fire Safety requires at least 50% of that flow when all water appliances – sinks, toilets, showers, equipment cleaning hoses, etc. – are in use at the same time. To comply, an 800-gallon tank and pump costing $50,000 were installed.

In addition to what was anticipated in the original building plans, Hagenbarth asked the selectmen’s authority to purchase unanticipated extras amounting to around $113,000. Of those a specialized locking and alarm systems, connecting to a sophisticated radio system and some air cleansing equipment are mandated by the state.

“We really don’t have a choice about buying those,” Hagenbarth told the board Tuesday.

Haff made a motion to authorize the additional $113,000, which the board approved unanimously.

Do you want to submit feedback to the editor?

Send Us An Email!

Related Posts

Stockbridge resident makes World MastersFly Fishing team

May 15, 2024
U.S. team of five will compete in the Czech Republic May 19-24 By Katy Savage A Stockbridge resident is casting up to test his fishing skills at the 2024 World Masters Fly Fishing Championships. Matt Stedina is one of five people who made the U.S. team. He’s currently in the Czech Republic preparing for the…

Killington Cup to return in 2024 

May 15, 2024
Killington Resort is slated to kick off the 2024-25 Audi FIS Ski World Cup races in the U.S., hosting the Stifel Killington Cup for the eighth time over Thanksgiving weekend. Over 40,000 fans are expected to cheer on the fastest female ski racers in the world, including six-time Stifel Killington Cup Slalom champion and winningest…

Robert Hecker appointed to Killington Select Board

May 15, 2024
By Curt Peterson Robert Hecker has been appointed to take Steve Finneron’s seat on the Killington Select Board. The announcement came after an executive session Monday night May 13. The position lasts until next Town Meeting Day vote, when voters will choose the person to fulfill the remaining year of Finneron’s term.  Hecker was one…

Vermont Legislature adjourns after a contentious 2024 session

May 15, 2024
Session was shaped by debates over property taxes, housing shortages, flood recovery and public safety By Sarah Mearhoff and Shaun Robinson/VTDigger After a tumultuous day of dealmaking on housing, land use and property tax measures, the Vermont Legislature adjourned its 2024 session in the early hours of Saturday morning, May 11. The Senate gaveled out at 1:18 a.m.…