On April 26, 2017

VTrans outlines bridge construction plans

Walker Bridge and Branch Brook Bridge work to start May 1

By Stephen Seitz

LUDLOW—Hoping for the smoothest possible project, officials from the Vermont Agency of Transportation outlined their plans for replacing the Walker Bridge, which is the gateway to downtown Ludlow, at a public forum Thursday, April 20.

At about the same time, a smaller bridge over Branch Brook will also be rehabilitated.

“Route 103 is a major west route between I-91 and U.S. [Route] 7, located in the heart of downtown Ludlow,” Michael Chenette, the assistant project manager, told the sparse crowd at the forum. “It serves as a major truck route between the east and west sides of Vermont.”

The Walker Bridge, or Bridge 25, was constructed in 1928. It is 86 feet long with two 43-foot spans. From curb to curb it’s 23.8 feet, with two 5-foot wide sidewalks.

“It’s in poor condition, with visible deterioration on the deck,” Chenette said. “It’s definitely time to replace. The bridge will be completely replaced.”

The next bridge, he said, will be larger and safer.

“The bridge will be 8 feet wider than it is now,” Chenette said, “which will allow for significantly larger shoulders, which will be a lifesaver. It’ll be about 10 feet wider on each side. It’s going to have a conventional cast- in-place deck. Some of those components will be built off-site. Construction of the new bridge has actually already started, but it won’t be brought to the site until later on.”

Chenette said there would be two weeks of prep work before the bridge is actually closed on June 10. Starting on May 27, the agency will be installing traffic control signs and message boards, controlling erosion, and preparing the access and staging areas. The bridge will have alternating one-way traffic during daytime. The working day during this period will include weekends, and 10-12 hours during daylight.

Once the bridge is closed, contractor Cold River Bridges will remove existing the bridge. They will drive steel piles for abutments, set steel girders, and form and pour the concrete deck. They will also attend to drainage, waterline, sidewalks and light poles, and cleanup.

There are plans during the closure to have 24-hour work cycles, which prompted one man in the audience to ask if that included the pile drivers.

Cold River Bridges spokesman Jim Hollar said that would not be a problem.
“It’ll be from 7 a.m. to 7 p.m., or 7 a.m. to 8 p.m.,” he said. “But they’re not going that deep. It’ll probably be two days on one side, and two days on the other. It’s not like we’re driving them to China.”

Traffic will be detoured around the project. Chenette said truck traffic would be diverted from Route 103 in Chester to Route 11 to Londonderry, where trucks will be able to take Route 100 into Ludlow. The detour adds 17.7 miles to the truck trip, Chenette said.

“We’ll be reaching out to trucking companies and bus companies to let them know what’s happening,” he said. “Hopefully, they can seek out the best routes for them, depending on where they’re coming from.”

Local traffic will be diverted to High Street from Gleascott Avenue to North Depot Street back to Main Street, making the trip .02 miles longer.

“Elm Street will be blocked off at one end, and going over to Gleascott Avenue,” Chenette said. “That’s going to become one-way, with some temporary parking. Some of the parking in the area will be taken away, so we’re going to try to accommodate some of that.”

“Have you given any consideration to signage?” asked one resident. “There’s a 90 degree turn onto Route 100 in Ludlow. We’ve had a couple of vehicles lose brakes coming into that, and is there any signage to indicate sharp turns ahead?”

“We can look at the sign package,” Chenette replied. “We can check on that and talk about doing something.”

Resident Sharon Bixby suggested, “We should change the timing on the Depot Street stoplight so people won’t have to wait for long periods.”

Once the bridge is in place, alternating traffic returns to the area as permanent traffic signs and the bridge railing are installed, and the lanes need to be striped. Chenette said this would take about two weeks.

The Branch Brook project won’t be nearly as elaborate or take as long to complete, according to VTrans project manager Todd Sumner.

“The goal is to have that bridge open for traffic before Memorial Day weekend,” he said.

Built in 1966, the Branch Brook bridge is a single span concrete deck on steel beams.

“The deck is in poor condition,” Sumner said, “but the steel beams and abutments are in good condition.”

The plan is to replace the deck using the existing beams and abutments. The new bridge will be an 82-foot single span.

Construction begins May 1. On May 15, the bridge will close for 10 days. Detours for all vehicles will be to Route 100, U.S. 4, U.S. 7, and Vermont Route 103, or 53.5 miles.

There will be weekly updates on the project. Those interested may sign up for e-mail alerts at https://southcentralvtbridges.vtransprojects.vermont.gov/bridge_projects/ludlow.

Do you want to submit feedback to the editor?

Send Us An Email!

Related Posts

Robert Hecker appointed to Killington Select Board

May 15, 2024
By Curt Peterson Robert Hecker has been appointed to take Steve Finneron’s seat on the Killington Select Board. The announcement came after an executive session Monday night May 13. The position lasts until next Town Meeting Day vote, when voters will choose the person to fulfill the remaining year of Finneron’s term.  Hecker was one…

Town resolves eminent domain 

May 15, 2024
Deal with landowner called ‘win-win’ By Polly Mikula The town of Killington will not pursue an eminent domain hearing scheduled for May 20, having recently resolved the case with the landowner.  Eva Nagymihaly and her sister, Theresa Rust, own land on the east side at the base of Killington Road to the intersection with Route…

Logging company fined for wetland and water quality impacts in Bridgewater, Thetford

May 15, 2024
The Agency of Natural Resources Dept. of Environmental Conservation (DEC) and Vermont Forests, Parks, and Recreation (FPR) announced May 8 that Thomson Timber Harvesting and Trucking LLC (Thompson Timber), a company that performs logging activities in Vermont, was fined $32,550 for violating the Vermont Wetland Rules and failing to follow acceptable management practices (AMPs) for…

Wonderfeet Kids’ Museum celebrates expansion

May 15, 2024
By Polly Mikula Saturday, May 11, Wonderfeet Kids’ Museum held a grand opening celebration from 10 a.m.-2 p.m. on Merchants Row downtown. While the museum relocated to its current location (66 Merchants Row) last spring, this was the first time the organization has celebrated that expansion. The move allowed Wonderfeet Kids’ Museum to tripled in size with new…