On November 22, 2016

Sherburne Memorial Library roof upgrades hit impasse

By Evan Johnson
KILLINGTON—Town officials say details regarding liability and insurance are upholding progress on fixing a leaky roof over the Killington town library.
Library director Jane Ramos said the need is dire. “The shingles have failed,” she said. “If you look at the back of the building, you’ll see the shingles are falling off the roof and into the grass. It looks like we’re not going to last the winter.”
Ramos said while they have seen leaks in the roof that was built in 1999, none have been serious.
The town approved $200,000 for the roof project last year. The sole bid for the project came from Roaring Brook Constructors, Inc., at $245,000, and the library would shoulder the additional costs.
One big issue is a builder’s risk insurance policy that would indemnify the contractor if something happened to the library during construction. The library had arranged a policy through its insurer for $661 that would cover the amount of the contract, but the contractor wants the town to purchase a $2,245,700 policy at a minimum earned premium of $5,000.
The contractor also requested a waiver of subrogation from the town that would prevent the town from seeking damages should any damage occur to the library during construction.
Ramos said late November could be too late to start a roof repair project. Should the town and the contractor fail to strike a deal, Ramos said they may have to wait until the spring to seek another bid. The town roads department has agreed to oversee the maintenance of the roof during the winter and will work to remove snow after storms.
“I’m trying to leave the door open if anybody moves off their respective positions,” said Killington Town Manager Deborah Schwartz at the last town meeting.
In the meantime, Ramos said, “We’ve just got to deal with what we’ve got.”

Do you want to submit feedback to the editor?

Send Us An Email!

Related Posts

Killington Resort announces staff promotions, management additions 

June 4, 2025
Josh Reed  Josh Reed has moved into the role of communications manager. Reed has been part of the Killington team since 2021, most recently serving as a ticket and reservation supervisor, where he was recognized for his thoughtful leadership and commitment to the mountain. Reed has over 20 years of sales and marketing leadership experience…

CEDRR receives $2,500 Smart Growth Award

June 4, 2025
The Vermont Natural Resources Council announced the latest grant recipients for the Small Grants for Smart Growth program, May 27. Grantee selections are made on a rolling basis. The committee chose the Bridport Housing Task Force, the Chamber & Economic Development of the Rutland Region (CEDRR), and the South Burlington Energy Committee to be awarded a combined $6,750 in the most recent…

Big Brothers Big Sisters of Vermont celebrates 50 years of mentorship and community impact

June 4, 2025
2025 marks a significant milestone for Big Brothers Big Sisters of Vermont (BBBSVT), which is celebrating 50 years of empowering youth through meaningful, one-on-one mentoring relationships across the Green Mountain State. Founded in 1975 through Youth Services, BBBSVT has matched thousands of “Littles” with caring adult “Bigs,” fostering relationships that help young people realize their…

Motorized forage harvester falls into Hartland gorge

June 4, 2025
By Curt Peterson A convoy of haying equipment and workers started out from Braintree on Monday, May 26, to harvest 47 acres across from Harpoon Brewery for landowner John McGrail of Shepherds Brook Farms. Their journey was cut short when a 20-foot tall, 27-ton self-propelled John Deere forage harvesting machine, avoiding collision with an oncoming…