TDI New England approved for $1.2 billion transmission project ending in Ludlow

By Mike Polhamus, VTDigger.org

The Public Service Board on Tuesday, Jan. 5, approved a $1.2 billion utility transmission project from Canada to Ludlow.

TDI New England plans to build a 1,000-megawatt transmission line under Lake Champlain that will feed the southern New England power grid. The board said it issued a certificate of public good to TDI because the project diversifies energy sources, reduces greenhouse gas emissions, creates new jobs, generates tax revenue and potentially supplies cheaper energy.

The Montpelier-based Conservation Law Foundation agreed last year not to oppose the project after it was able to negotiate large payments from the utility for Lake Champlain cleanup.

“TDI New England did a good job of showing that large energy projects can meet high environmental standards,” said CLF Senior Attorney Sandra Levine. “There are a number of transmission projects in the region being evaluated and considered; this isn’t an endorsement of this project, it’s just a recognition that they did a lot of things right, and I think they have set in some ways a model for other projects.”

An instructive comparison can be made between this project and the Vermont Gas Systems natural gas pipeline proposed for Addison County, Levine said.

The pipeline has met steady opposition from AARP and landowners, she said, because Vermont Gas has done a poor job of evaluating the pipeline’s impacts and hasn’t been transparent enough with ratepayers and the board about costs.

“When you look at the two side by side, Vermont Gas is still facing problems with permitting, and the TDI project has received its permits,” she said.

The firm merely followed sound business practices, said TDI New England’s CEO Donald Jessome.

The project is being built not out of necessity, as is the case with some power projects, but rather for economic reasons, and as such “there’s no question we have a higher burden to the states we’re traversing to demonstrate public good,” Jessome said.

Early in the project’s development, the firm reached out to stakeholders, including environmental organizations, state regulatory bodies and others, Jessome said. “We totally understand that in the development world we have to listen to all the stakeholders,” he said.

TDI plans to pay hundreds of millions of dollars toward environmental cleanup efforts over the project’s lifespan, and Jessome said, “We see that as a cost of doing business.” Large portions of those monies were secured through negotiations with the Conservation Law Foundation.

The cable will run from the Canadian border to Ludlow, sunk for most of that length beneath Lake Champlain.

The cable will carry 1,000 megawatts, roughly the amount of power consumed by the entire state of Vermont. If it is constructed, Vermont will host the cable, and most of the electricity will be transmitted to southern New England. Vermont will have the option to purchase up to 200 megawatts from the cable.

The cable is expected to carry power from dams and wind turbines.

TDI has agreed to pay a minimum of $283.5 million over the 40-year lifespan of the project for Lake Champlain phosphorus cleanup, habitat restoration and recreational improvements—$121.5 million more than was originally proposed. Some of that money would also go to the state’s Clean Energy Fund.

TDI has also agreed to pay the state’s transmission utility, Vermont Electric Power Co. (VELCO), $136 million–$2.5 million annually–over 40 years. That money is expected to be used to reduce electric rates, according to state officials.

TDI New England is a subsidiary of financial firm Blackstone Group, which manages more than $200 billion in assets. The firm anticipates permitting will take until mid-2016, with major construction beginning in 2018. If  the project moves forward, then the 1,000-megawatt transmission line is expected to carry power by 2019.

Do you want to submit feedback to the editor?

Send Us An Email!

Related Posts

Vermont Legislature adjourns after a contentious 2024 session

May 15, 2024
Session was shaped by debates over property taxes, housing shortages, flood recovery and public safety By Sarah Mearhoff and Shaun Robinson/VTDigger After a tumultuous day of dealmaking on housing, land use and property tax measures, the Vermont Legislature adjourned its 2024 session in the early hours of Saturday morning, May 11. The Senate gaveled out at 1:18 a.m.…

New data shows first decrease in Vermont opioid deaths since 2019

May 15, 2024
Overdose deaths in Vermont have decreased for the first time since 2019. According to the Dept. of Health’s newly released Annual Fatal Overdose Report, opioid-related overdoses resulted in the death of 231 Vermonters in 2023, a 5% drop from 2022 when 244 Vermonters died. The overdose report includes data on Vermonters who died of any drug…

Safe bet

May 15, 2024
After a week of long days and late nights, the regular session of the 2024 Vermont Legislature adjourned early Saturday morning just after 2 a.m. My best guess in the annual adjournment pool was 6:30 p.m. Friday evening, which turned out to be way too optimistic. When the Legislature finishes its work for the session,…

A lot accomplished this Legislative session

May 15, 2024
Vermont’s 2023-24 Legislative Biennium ended in the wee hours of Saturday morning May 11. The Senate gaveled out at 1:18 a.m. and the House about 2 a.m. This has been a hard session. It was begun in the wake of a natural disaster, with a state recovering from terrible flooding. Despite these challenges we managed…