TDI, CLF reach agreement on transmission line project

By Morgan True, VTDigger.org

The Conservation Law Foundation has agreed not to oppose a 154-mile high-voltage transmission cable that would run beneath Lake Champlain in exchange for an increase the value of a benefits package the developer offered the state.

The agreement was filed Friday, June 12, with the Public Service Board as part of TDI New England’s effort to obtain a Certificate of Public Good for the proposed $1.2 billion transmission line. The cables would carry hydroelectric and wind power generated in Canada to metropolitan areas of the United States.

The company has agreed to pay a minimum of $283.5 million over the 40-year lifespan of the project for Lake Champlain phosphorus cleanup, habitat restoration and recreational improvements — $121.5 million more than was originally proposed.

Chris Killian, Vermont director of CLF, called the increase “substantial” and said the agreement better defines how the money will be spent, which “dramatically” enhances the public benefit of the project.

TDI will make two upfront payments of $1 million to the state, according to Killian.

In a separate agreement, TDI has also agreed to pay the state’s transmission utility, Vermont Electric Power Co. (VELCO), $2.5 million annually over 40 years. That money is expected to be used to reduce electric rates, according to state officials.

TDI New England anticipates permitting will take until mid-2016, with major construction beginning in 2018. If the New England Clean Energy Link moves forward, then the 1,000-megawatt transmission line is anticipated to be carrying power by 2019.

Do you want to submit feedback to the editor?

Send Us An Email!

Related Posts

BlueCross BlueShield of Vt seeks to raise insurance rates further

July 24, 2024
If accepted, the new request would increase premiums for individual health plans by 21% and small group plans by 24% in 2025 By Peter D'Auria/VTDigger BlueCross BlueShield of Vermont is seeking to raise health insurance premiums by an additional 4.3% next year, further increasing a request for already near-record-high rate hikes.  The proposed increase would increase premiums for individual…

Gravel rides tell Vermont’s story top to bottom on VTXL cycling route

July 24, 2024
By Charlotte Oliver/Community News Service Editor’s note: The Community News Service is a program in which University of Vermont students work with professional editors to provide content for local news outlets at no cost. From the top of the Northeast Kingdom down toward the Berkshires, the VTXL carves a path the length of Vermont. The biking route takes…

Living with wildlife: Bats in your house?

July 24, 2024
Bats are everywhere! It may feel that way to some of Vermont’s human residents. Summer is when some species of bats gather in colonies to raise their young in human-made structures such as houses, barns, office buildings, and bat houses, but fall is the safe time to get them out. “Summer is the time of…

Annual count shows rise in homelessness

July 24, 2024
The 2024 census recorded 3,458 people homeless in Vermont, a nearly 5% increase over the number tallied in January 2023 By Carly Berlin Editor’s note: This story, by Report for America corps member Carly Berlin, was produced through a partnership between VTDigger and Vermont Public. The number of unhoused Vermonters living without shelter jumped last year,…