On June 17, 2015

TDI, CLF reach agreement on transmission line project

By Morgan True, VTDigger.org

The Conservation Law Foundation has agreed not to oppose a 154-mile high-voltage transmission cable that would run beneath Lake Champlain in exchange for an increase the value of a benefits package the developer offered the state.

The agreement was filed Friday, June 12, with the Public Service Board as part of TDI New England’s effort to obtain a Certificate of Public Good for the proposed $1.2 billion transmission line. The cables would carry hydroelectric and wind power generated in Canada to metropolitan areas of the United States.

The company has agreed to pay a minimum of $283.5 million over the 40-year lifespan of the project for Lake Champlain phosphorus cleanup, habitat restoration and recreational improvements — $121.5 million more than was originally proposed.

Chris Killian, Vermont director of CLF, called the increase “substantial” and said the agreement better defines how the money will be spent, which “dramatically” enhances the public benefit of the project.

TDI will make two upfront payments of $1 million to the state, according to Killian.

In a separate agreement, TDI has also agreed to pay the state’s transmission utility, Vermont Electric Power Co. (VELCO), $2.5 million annually over 40 years. That money is expected to be used to reduce electric rates, according to state officials.

TDI New England anticipates permitting will take until mid-2016, with major construction beginning in 2018. If the New England Clean Energy Link moves forward, then the 1,000-megawatt transmission line is anticipated to be carrying power by 2019.

Do you want to submit feedback to the editor?

Send Us An Email!

Related Posts

The anticipated ‘Dec. 1 letter’ from the Vermont tax dept. projects 5.9% property tax increase

December 4, 2024
By Ethan Weinstein/VTDigger and Polly Mikula Vermonters can expect a 5.9% average increase in education property taxes next year absent major changes, according to the annual forecast from Craig Bolio, Vermont’s tax commissioner. The news arrived Monday, Dec. 2, in the form of the “Dec. 1 letter,” an annual projection required by law that represents the…

Vermont receives $5.3 million in federal grants to expand internet access across the state

November 27, 2024
By Klara Bauters / VTDigger Vermont has been awarded $5.3 million from the federal government to implement its Digital Equity Plan — which outlines how the state will provide individuals and communities with the tools and skills necessary to benefit from meaningful access to affordable, reliable, high-speed internet service. “Internet and broadband. It’s no longer…

Experts fear Trump environmental policies could undermine Vt’s efforts

November 27, 2024
By Emma Cotton/VTDigger As Donald Trump prepares to return to the presidency, experts worry that his climate and environmental policy goals could destabilize ongoing work in Vermont. The president-elect campaigned on tossing out policies related to climate change and loosening or abandoning environmental regulations. As a small state, Vermont leans on federal funding and regulatory frameworks…

VTSU sees 20% enrollment growth in plumbing, electrical apprenticeship programs

November 27, 2024
As the state kicked off Apprenticeship Week last week, Vermont State University (VTSU) announced that its plumbing and electrical registered apprenticeship programs have grown over 20% in two years. Enrollment for the current academic year is at a record high of over 870 apprentices after multiple years of sustained growth. “Vermont State University is dedicated…