State presents plans for replacing Killington bridge on Route 4

Portion of busy thoroughfare to close for 10 days

By Polly Lynn

KILLINGTON — At the past Selectboard Meeting on Tuesday, May 5, several members from the Vermont Agency of Transportation, including Jennifer Fitch, structures project manager, and Gary Sweeny, project engineer, reviewed and discussed the planned replacement of Bridge #33, which is scheduled to take place during the summer of 2018.

The bridge, located just east of Skyeship Gondola on US Route 4, is in poor condition and has been deemed “structurally deficient” by the state. The bridge was built in 1956 and is approximately 69 feet long and 30 feet wide.

Fitch reviewed the other options for bridge repair, including a deck replacement, and deck and superstructure replacement. Ultimately, the state decided that a full bridge replacement would be best. “We really want to get in and then stay out,” she said.

During the estimated 10 day project, the road will be closed. Additionally, the project will result in traffic disruptions, including periodic lane closures, for a couple of weeks before and after the closure.

There will be a local detour, 1.6 miles around via Mission Farm Road; but the major detour for regional traffic and all trucks will be 48 miles, via Routes 100, 103, 7 and 4 passing through Plymouth, Ludlow, Clarendon, Rutland and Mendon, respectively.

According to a recent state traffic study, Bridge #33 carries an average of 5,900 vehicles daily, with a maximum of 820 per hour. Trucks make up 15.4 percent of the traffic.

However, many local attendees questioned these traffic estimates, noting that the averages are not very useful, as the volumes fluctuate greatly depending on the day of the week and the season.

Rev. Lee Alison Crawford, pastor at Church of Our Saviour on Mission Farm Road, was concerned about the volume of local traffic, saying it would be “interesting.” She noted that occasionally an accident has forced Route 4 traffic onto Mission Farm Road as a detour for short periods of time and vehicles always drive too fast.

The timing for the construction will be determined by a variety of factors, including when fish are spawning in the river and Killington’s event such as the Stage Race, Century Ride, Vermont Challenge, Killington Classic and Spartan Race.

The replacement bridge will be 10 feet wider than the current structure, at 40 feet with two 12-foot travel lanes and two 8-foot shoulders, making popular activities such as walking or biking safer.

The lifespan for the proposed bridge is 80+ years.

The state will pay for the cost of the new bridge and will also have a small allotment to help the town offset any repairs or costs (including enforcement) that are needed due to construction, Killington Town Manager Seth Webb said.

bridge #33 - Scan 1

Do you want to submit feedback to the editor?

Send Us An Email!

Related Posts

Yale student wrote her thesis on Vermont’s school mergers, found they don’t save much

June 12, 2024
By Ethan Weinstein/VTDigger While studying economics and education at Yale University, Grace Miller found a surprise topic on the agenda: Vermont’s one-of-a-kind school funding formula.  The 22-year-old from Newport and her classmates learned about the Brigham decision, a 1997 Vermont Supreme Court case that found the state’s education finance system was unconstitutional.  In response to the case, the…

Killington road work extends into Saturday morning

June 12, 2024
Drilling and blasting will continue this week at the intersection of Route 4 and Killington Road in Killington. A detour remains in place via West Hill Road.  As the project approaches the scheduled end date of July 8, work to haul out rock will occur on Saturdays till about noon time going forward, Markowski Excavating,…

Hartland board to propose new vendors’ ordinance

June 12, 2024
By Curt Peterson The Hartland Select Board refined a proposed new Vendors’ Ordinance to replace the original that’s been in effect since 1996. According to Town Manager John Broker-Campbell, “There are minor changes which will hopefully help to clear up any confusion or ambiguity on the applicability of the ordinance.”   The Select Board will next…

Building a stronger Killington-Rutland community:Essential nonprofits tackle tough issues

June 12, 2024
Vermont’s vibrant spirit thrives on a network of over 7,000 nonprofits; some 1,500 of them in the Killington-Rutland region alone. Considering that number, it’s not surprising that some of these organizations prompt the question: “Why does that nonprofit exist?” Yet, the ones that tackle tough issues and enrich lives spark admiring comments, like “Imagine how…